The Influence of Time Management Quality on the Timeliness Story Private House Construction Project Using the Critical Path Method

This research investigates how the quality time management affect the time delivery of a two-floor private house project in Samarinda. Using the Critical Path Method, efficient time management is an important thing as it directly impacts project cost, quality, and client satisfaction. CPM was used in this research to spot tasks that might delay the project. Data collection involved observation, interviews, and documentation, which were then analyzed using a project network diagram. The conclusions reveal that this project can be shortened from 458 to 383 days through the optimalization of critical activities which resulting in a 16.38%-time efficiency without reducing construction quality. This study also identifies common challenges encountered on-site, such as limited resources, mid-project design changes, and external interferences.

Authors

Publication Details

Journal
International Journal of Multidisciplinary Research and Growth Evaluation
Published
2025-01-01
DOI
https://doi.org/10.54660/.ijmrge.2025.6.4.71-76
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

The Influence of Time Management Quality on the Timeliness Story Private House Construction Project Using the Critical Path Method

Tandi Kadang, Heldina Pristanti, Diah Ayu Maharani, Surahman Surahman et al.
International Journal of Multidisciplinary Research and Growth Evaluation
Construction Project Management and Performance
article

The Influence of Time Management Quality on the Timeliness Story Private House Construction Project Using the Critical Path Method

Tandi Kadang, Heldina Pristanti, Diah Ayu Maharani, Surahman Surahman, Della OC Kalangit, Regina Syavitri
article en

Abstract

This research investigates how the quality time management affect the time delivery of a two-floor private house project in Samarinda. Using the Critical Path Method, efficient time management is an important thing as it directly impacts project cost, quality, and client satisfaction. CPM was used in this research to spot tasks that might delay the project. Data collection involved observation, interviews, and documentation, which were then analyzed using a project network diagram. The conclusions reveal that this project can be shortened from 458 to 383 days through the optimalization of critical activities which resulting in a 16.38%-time efficiency without reducing construction quality. This study also identifies common challenges encountered on-site, such as limited resources, mid-project design changes, and external interferences.

International Journal of Multidisciplinary Research and Growth EvaluationVol. 6(4)
Openalex Percentile: Top 82%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.