The Impact of Flooding on Road Infrastructure Construction in Rwanda: A Case of Huye-Kibeho Road Construction

Flooding risks pose significant challenges to road infrastructure construction globally, causing delays, cost overruns, and reduced durability. In Rwanda, these challenges are particularly evident due to high rainfall intensity, frequent floods, and inadequate drainage systems, which exacerbate road damage and soil erosion. The Huye-Kibeho road construction project in Southern Rwanda has faced substantial delays and cost increases as a result of these flooding risks. This study examines the impact of flooding risks on road infrastructure construction, with a focus on the Huye-Kibeho road project. The research employs a descriptive survey design, utilizing both quantitative and qualitative methods. Data was collected through structured questionnaires and key informant interviews. The structured questionnaires, incorporating both closed-ended and Likert scale questions, will capture quantitative data, while interviews will provide deeper insights into the flooding-related challenges faced during construction. The analysis will include descriptive statistics (e.g., means, frequencies, and percentages) to summarize the findings, and inferential statistics, specifically correlation and regression analysis, was used to assess the relationship between flooding risk factors and road infrastructure performance. The regression analysis indicates a significant relationship between flooding factors and road construction, with flooding factors explaining 62.5% of the variance in construction delays and cost overruns (R² = 0.625, F (6, 137) = 378.171, p < 0.001). Qualitative data from interviews was analyzed thematically to identify recurring patterns related to the impact of flooding risks. The combination of these methods provides a comprehensive understanding of the issue. The study confirms that flooding risks have a substantial impact on road infrastructure construction, specifically on the Huye-Kibeho road project. The findings highlight significant delays and cost overruns linked to flooding factors, including high rainfall intensity, flood frequency, floodwater depth, soil erosion, drainage system inefficiencies, and the region’s topography. These challenges not only hinder the construction progress but also jeopardize the long-term durability and lifespan of the road. Based on the findings, it is recommended that the Huye-Kibeho road construction project implement enhanced flood mitigation measures, including the development of a robust drainage system, flood barriers, and soil stabilization techniques, to effectively manage the flooding risks and minimize the impact on construction delays, cost overruns, and long-term road durability.

Authors

Institutions

Publication Details

Journal
Journal of Energy Environmental & Chemical Engineering
Published
2025-06-18
DOI
https://doi.org/10.11648/j.jeece.20251002.11
Primary Topic
Water Systems and Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

The Impact of Flooding on Road Infrastructure Construction in Rwanda: A Case of Huye-Kibeho Road Construction

Alexander Williams, James Kant
Journal of Energy Environmental & Chemical Engineering
Water Systems and Optimization
article

The Impact of Flooding on Road Infrastructure Construction in Rwanda: A Case of Huye-Kibeho Road Construction

Alexander Williams, James Kant
article en

Abstract

Flooding risks pose significant challenges to road infrastructure construction globally, causing delays, cost overruns, and reduced durability. In Rwanda, these challenges are particularly evident due to high rainfall intensity, frequent floods, and inadequate drainage systems, which exacerbate road damage and soil erosion. The Huye-Kibeho road construction project in Southern Rwanda has faced substantial delays and cost increases as a result of these flooding risks. This study examines the impact of flooding risks on road infrastructure construction, with a focus on the Huye-Kibeho road project. The research employs a descriptive survey design, utilizing both quantitative and qualitative methods. Data was collected through structured questionnaires and key informant interviews. The structured questionnaires, incorporating both closed-ended and Likert scale questions, will capture quantitative data, while interviews will provide deeper insights into the flooding-related challenges faced during construction. The analysis will include descriptive statistics (e.g., means, frequencies, and percentages) to summarize the findings, and inferential statistics, specifically correlation and regression analysis, was used to assess the relationship between flooding risk factors and road infrastructure performance. The regression analysis indicates a significant relationship between flooding factors and road construction, with flooding factors explaining 62.5% of the variance in construction delays and cost overruns (R² = 0.625, F (6, 137) = 378.171, p < 0.001). Qualitative data from interviews was analyzed thematically to identify recurring patterns related to the impact of flooding risks. The combination of these methods provides a comprehensive understanding of the issue. The study confirms that flooding risks have a substantial impact on road infrastructure construction, specifically on the Huye-Kibeho road project. The findings highlight significant delays and cost overruns linked to flooding factors, including high rainfall intensity, flood frequency, floodwater depth, soil erosion, drainage system inefficiencies, and the region’s topography. These challenges not only hinder the construction progress but also jeopardize the long-term durability and lifespan of the road. Based on the findings, it is recommended that the Huye-Kibeho road construction project implement enhanced flood mitigation measures, including the development of a robust drainage system, flood barriers, and soil stabilization techniques, to effectively manage the flooding risks and minimize the impact on construction delays, cost overruns, and long-term road durability.

Journal of Energy Environmental & Chemical EngineeringVol. 10(2)
University of Lay Adventists of Kigali (RW)
Openalex Percentile: Top 84%
Water Systems and Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.