Process time estimation for workstations in modular construction production line

Modular construction companies produce module components following a make-to-order process to realize client-defined customization requirements. This customization leads to varying process times of prefabricating module components at workstations, making it difficult for production line managers to accurately predict their process times for planning purposes. To address these challenges, this paper proposes a novel method that employs Deep Neural Networks, artificial neural networks, and multiple linear regression models for predicting workstation production process times at a module prefabrication plant. A Genetic Algorithm is employed to refine the structure of the Deep Neural Networks and find a near-optimum number of hyperparameters. In a case study, a wood-based wall panel production line is analyzed to demonstrate the use of the developed method and test its performance. The developed method for process time prediction is found to achieve a mean absolute error of less than 2.50 min for most workstations, with the symmetric mean absolute percentage error ranging between 22% and 28%. The research contributions of this study include the development of prediction models for all the workstations of the production line and the implementation of a Genetic Algorithm to find the near-optimal hyperparameters of Deep Neural Networks. This assists production managers in making data drive decisions and overcomes the reliance on experience-based methods for estimating process times and creating production plans.

Authors

Institutions

Publication Details

Journal
Journal of Information Technology in Construction
Published
2025-06-30
DOI
https://doi.org/10.36680/j.itcon.2025.044
Primary Topic
Manufacturing Process and Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Process time estimation for workstations in modular construction production line

SangHyeok Han, Angat Pal Singh Bhatia, Osama Moselhi
Journal of Information Technology in Construction
Manufacturing Process and Optimization
article

Process time estimation for workstations in modular construction production line

SangHyeok Han, Angat Pal Singh Bhatia, Osama Moselhi
article en

Abstract

Modular construction companies produce module components following a make-to-order process to realize client-defined customization requirements. This customization leads to varying process times of prefabricating module components at workstations, making it difficult for production line managers to accurately predict their process times for planning purposes. To address these challenges, this paper proposes a novel method that employs Deep Neural Networks, artificial neural networks, and multiple linear regression models for predicting workstation production process times at a module prefabrication plant. A Genetic Algorithm is employed to refine the structure of the Deep Neural Networks and find a near-optimum number of hyperparameters. In a case study, a wood-based wall panel production line is analyzed to demonstrate the use of the developed method and test its performance. The developed method for process time prediction is found to achieve a mean absolute error of less than 2.50 min for most workstations, with the symmetric mean absolute percentage error ranging between 22% and 28%. The research contributions of this study include the development of prediction models for all the workstations of the production line and the implementation of a Genetic Algorithm to find the near-optimal hyperparameters of Deep Neural Networks. This assists production managers in making data drive decisions and overcomes the reliance on experience-based methods for estimating process times and creating production plans.

Journal of Information Technology in ConstructionVol. 30
Concordia University (CA)
Openalex Percentile: Top 78%
Manufacturing Process and Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.