Woven Bag Production Scheduling With Heuristic Pour Algorithm and Earliest Due Date

PT. XYZ is a company engaged in manufacturing, especially in producing woven bags, which are plastic sacks made of Polypropylene (PP). PT. XYZ faces the problem of too long makespan time in the application of the First Come First Serve (FCFS) method. Although considered simple, FCFS is less efficient in complex production, especially with variations in processing time. As a result, jobs with longer processing times are often prioritized, resulting in delays in shorter jobs. This causes a longer total completion time and requires the implementation of a more efficient scheduling method to minimize makespan and improve production performance. The purpose of this study was to determine the optimal woven bag production job and to reduce makespan and delays in woven bag production with the Heuristic Pour Algorithm and Earliest due date (EDD) at PT. XYZ. From the calculation results using the first come first serve method with the job sequence 1-2-3-4-5-6, the total makespan value was 33119 or 551 hours 59 minutes. Meanwhile, the calculation using the heuristic pour algorithm method and Earliest due date (EDD) obtained the sequence of jobs 3-2-4-1-6-5 with a total makespan of 28528 minutes or 475 hours 28 minutes. The calculation using EDD also showed a decrease in lateness for each job, where the lateness of job 3 was the smallest, namely -10 days with a due date of 17 days. Based on this research, the percentage decrease in makespan value was 13.86%.

Authors

Institutions

Publication Details

Journal
Journal La Multiapp
Published
2025-06-30
DOI
https://doi.org/10.37899/journallamultiapp.v6i3.1971
Primary Topic
Scheduling and Optimization Algorithms
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Woven Bag Production Scheduling With Heuristic Pour Algorithm and Earliest Due Date

Ajeng Afriza, Rr. Rochmoeljati
Journal La Multiapp
Scheduling and Optimization Algorithms
article

Woven Bag Production Scheduling With Heuristic Pour Algorithm and Earliest Due Date

Ajeng Afriza, Rr. Rochmoeljati
article en

Abstract

PT. XYZ is a company engaged in manufacturing, especially in producing woven bags, which are plastic sacks made of Polypropylene (PP). PT. XYZ faces the problem of too long makespan time in the application of the First Come First Serve (FCFS) method. Although considered simple, FCFS is less efficient in complex production, especially with variations in processing time. As a result, jobs with longer processing times are often prioritized, resulting in delays in shorter jobs. This causes a longer total completion time and requires the implementation of a more efficient scheduling method to minimize makespan and improve production performance. The purpose of this study was to determine the optimal woven bag production job and to reduce makespan and delays in woven bag production with the Heuristic Pour Algorithm and Earliest due date (EDD) at PT. XYZ. From the calculation results using the first come first serve method with the job sequence 1-2-3-4-5-6, the total makespan value was 33119 or 551 hours 59 minutes. Meanwhile, the calculation using the heuristic pour algorithm method and Earliest due date (EDD) obtained the sequence of jobs 3-2-4-1-6-5 with a total makespan of 28528 minutes or 475 hours 28 minutes. The calculation using EDD also showed a decrease in lateness for each job, where the lateness of job 3 was the smallest, namely -10 days with a due date of 17 days. Based on this research, the percentage decrease in makespan value was 13.86%.

Journal La MultiappVol. 6(3)
University of Pembangunan Nasional Veteran Jawa Timur (ID)
Openalex Percentile: Top 78%
Scheduling and Optimization Algorithms
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Woven Bag Production Scheduling With Heuristic Pour Algorithm and Earliest Due Date — Ajeng Afriza, Rr. Rochmoeljati · Journal La Multiapp (2025) | TGRS Research Map | TGRS