Competitive negotiated procedure in Norwegian public infrastructure projects

Purpose Competitive negotiated procedure (CNP) is one of the procurement procedures that public owners can use. Despite the importance of the procedure, there is a notable lack of empirical studies investigating how it can be effectively implemented to improve future practices. The purpose of this paper is to suggest measures to improve the use of CNP in future projects. Design/methodology/approach In addition to the literature review, a document study and 42 semistructured in-depth interviews with key informants from four Norwegian public infrastructure projects were carried out. Findings CNP is a flexible procurement procedure used in projects with different characteristics. CNP clarifies uncertainties and creates a common understanding between the contracting parties in the procurement phase. Even though CNP is resource-demanding, all contracting parties saw the advantages of the procedure. Practical implications Three suggestions for future projects are developed: first, to exploit the flexibility that CNP offers; second, to adapt the procurement procedure to specific project characteristics; and third, to standardize the steps of CNP. For example, the evaluation step can be standardized to avoid legal problems, increase the contractors’ trust in the procedure and increase transparency. Social implications Effective application of CNP advances the efficient use of public resources for projects in public procurement to create long-term benefits for society. Originality/value The authors studied four projects that used CNP, aiming to provide firsthand information on how it can be implemented effectively to improve future practices.

Authors

Institutions

Publication Details

Journal
Journal of Public Procurement
Published
2025-06-27
DOI
https://doi.org/10.1108/jopp-06-2024-0070
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Competitive negotiated procedure in Norwegian public infrastructure projects

Paulos Abebe Wondimu, Asmamaw Tadege Shiferaw, Ola Lædre‌‌‌‌‌‌‌‌‌‌‌‌‌‌‌‌‌‌‌‌, Agnar Johansen
Journal of Public Procurement
Construction Project Management and Performance
article

Competitive negotiated procedure in Norwegian public infrastructure projects

Paulos Abebe Wondimu, Asmamaw Tadege Shiferaw, Ola Lædre‌‌‌‌‌‌‌‌‌‌‌‌‌‌‌‌‌‌‌‌, Agnar Johansen
article en

Abstract

Purpose Competitive negotiated procedure (CNP) is one of the procurement procedures that public owners can use. Despite the importance of the procedure, there is a notable lack of empirical studies investigating how it can be effectively implemented to improve future practices. The purpose of this paper is to suggest measures to improve the use of CNP in future projects. Design/methodology/approach In addition to the literature review, a document study and 42 semistructured in-depth interviews with key informants from four Norwegian public infrastructure projects were carried out. Findings CNP is a flexible procurement procedure used in projects with different characteristics. CNP clarifies uncertainties and creates a common understanding between the contracting parties in the procurement phase. Even though CNP is resource-demanding, all contracting parties saw the advantages of the procedure. Practical implications Three suggestions for future projects are developed: first, to exploit the flexibility that CNP offers; second, to adapt the procurement procedure to specific project characteristics; and third, to standardize the steps of CNP. For example, the evaluation step can be standardized to avoid legal problems, increase the contractors’ trust in the procedure and increase transparency. Social implications Effective application of CNP advances the efficient use of public resources for projects in public procurement to create long-term benefits for society. Originality/value The authors studied four projects that used CNP, aiming to provide firsthand information on how it can be implemented effectively to improve future practices.

Journal of Public ProcurementVol. 25(4)
Norwegian Public Roads Administration (NO), Norwegian University of Science and Technology (NO), Norwegian University of Life Sciences (NO)
Openalex Percentile: Top 82%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.