An Implementation Scheme for Large-Scale Data Center to Participate in Virtual Power Plant in Shanghai

Shanghai is the first city to start Virtual Power Plant (VPP) business in China and there are several large-scale data centers located in Shanghai. In 2024 data center's participation in VPP made fundamental progress. In this paper, the operation organization chart, process, price and features of demand response program within VPP framework in Shanghai are introduced. The advantages and disadvantages of 2 basic schemes for large-scale data center to participate in demand response are analyzed and therefore the scheme based on backup distributed diesel generator is selected according to its fitness for VPP's features. A concrete implementation scheme suitable for electrical connection topology of a large-scale data center is designed in details and really conducted during the demand response operation period this year in Shanghai. The operation result in the actual use case shows this scheme is effective, valuable and replicable for large-scale data centers in VPP application scenario around China.

Authors

Publication Details

Published
2025-04-15
DOI
https://doi.org/10.1109/acpee64358.2025.11041253
Primary Topic
Smart Grid and Power Systems
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

An Implementation Scheme for Large-Scale Data Center to Participate in Virtual Power Plant in Shanghai

Jia-Yi Yang, Jinshuang Hu, Liqiang Yuan, Weiqing Sun et al.
Smart Grid and Power Systems
article

An Implementation Scheme for Large-Scale Data Center to Participate in Virtual Power Plant in Shanghai

Jia-Yi Yang, Jinshuang Hu, Liqiang Yuan, Weiqing Sun, Shuaishuai Liu, Maeng Ho Yang
article en

Abstract

Shanghai is the first city to start Virtual Power Plant (VPP) business in China and there are several large-scale data centers located in Shanghai. In 2024 data center's participation in VPP made fundamental progress. In this paper, the operation organization chart, process, price and features of demand response program within VPP framework in Shanghai are introduced. The advantages and disadvantages of 2 basic schemes for large-scale data center to participate in demand response are analyzed and therefore the scheme based on backup distributed diesel generator is selected according to its fitness for VPP's features. A concrete implementation scheme suitable for electrical connection topology of a large-scale data center is designed in details and really conducted during the demand response operation period this year in Shanghai. The operation result in the actual use case shows this scheme is effective, valuable and replicable for large-scale data centers in VPP application scenario around China.

Openalex Percentile: Top 87%
Smart Grid and Power Systems
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

An Implementation Scheme for Large-Scale Data Center to Participate in Virtual Power Plant in Shanghai — Jia-Yi Yang, Jinshuang Hu, et al. · (2025) | TGRS Research Map | TGRS