Time management with quality control in construction projects by critical chain project management

Good quality control and effective time management are the key for infrastructure projects, particularly for mega projects such as metro rail systems, where there are several dependencies, limited resources, and external uncertainties that result in considerable delays. The Mumbai Metro Line 9 project, a Line 7 extension from Dahisar (East) to Mira Bhayandar and Andheri to CSIA, is facing schedule overruns at present due to different project constraints. This study explores the practice of applying Critical Chain Project Management (CCPM) as a replacement for the conventional Critical Path Method (CPM) applied in the initial project scheduling. The study identifies the major scheduling constraints, resource allocation issues, and quality control practices. Through the incorporation of CCPM practices such as buffer management and optimal resource allocation, this study presents a new scheduling method that increases the project efficiency. A comparison between CPM and CCPM illustrates how CCPM can result in quicker project completion with high standards of quality.

Authors

Institutions

Publication Details

Journal
IET conference proceedings.
Published
2025-06-27
DOI
https://doi.org/10.1049/icp.2025.1600
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Time management with quality control in construction projects by critical chain project management

Nisha N. Parmar, Mamta B. Rajgor
IET conference proceedings.
BIM and Construction Integration
article

Time management with quality control in construction projects by critical chain project management

Nisha N. Parmar, Mamta B. Rajgor
article en

Abstract

Good quality control and effective time management are the key for infrastructure projects, particularly for mega projects such as metro rail systems, where there are several dependencies, limited resources, and external uncertainties that result in considerable delays. The Mumbai Metro Line 9 project, a Line 7 extension from Dahisar (East) to Mira Bhayandar and Andheri to CSIA, is facing schedule overruns at present due to different project constraints. This study explores the practice of applying Critical Chain Project Management (CCPM) as a replacement for the conventional Critical Path Method (CPM) applied in the initial project scheduling. The study identifies the major scheduling constraints, resource allocation issues, and quality control practices. Through the incorporation of CCPM practices such as buffer management and optimal resource allocation, this study presents a new scheduling method that increases the project efficiency. A comparison between CPM and CCPM illustrates how CCPM can result in quicker project completion with high standards of quality.

IET conference proceedings.Vol. 2025(7)
Parul University (IN)
Industry, innovation and infrastructure
Openalex Percentile: Top 84%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Time management with quality control in construction projects by critical chain project management — Nisha N. Parmar, Mamta B. Rajgor · IET conference proceedings. (2025) | TGRS Research Map | TGRS