Assessment of Maintenance Performance Level of Selected Hydropower Plants in Tanzania

Despite significant progress in increasing electricity access to over 78%, electricity reliability in Tanzania remains a concern, with frequent power outages reported. Maintenance issues in hydropower plants have been identified as a critical factor contributing to this problem. However, the specific maintenance performance levels have not been fully assessed. This study conducts a comprehensive evaluation of the maintenance performance of four key hydropower plants: Kidatu (204 MW), Kihansi (180 MW), Mtera (80 MW), and New Pangani Falls (68 MW). Data collected from staff surveys and maintenance records between 2018 and 2022 were used in the study. Although staff demonstrated a reasonable awareness of the hydropower plants Key Performance Indicators (KPIs), with a minimum mean score of 3.66, the findings reveal underperformance across all plants, with a heavy reliance on reactive rather than proactive maintenance. Low plant availability (89%), insufficient planned work (42%), and excessive unplanned work (55%) were recorded. High Mean time to Repair and frequent failures, particularly at New Pangani Falls, were also observed. This research underscores the importance of strategic maintenance improvements to enhance the reliability and efficiency of Tanzania's hydropower sector.

Authors

Publication Details

Journal
Tanzania Journal of Engineering and Technology
Published
2025-06-20
DOI
https://doi.org/10.52339/tjet.v44i1.1272
Primary Topic
Power System Reliability and Maintenance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Assessment of Maintenance Performance Level of Selected Hydropower Plants in Tanzania

Mahamudu Hussein Mtebwa, Mathew Joachim Bundala
3 links
Tanzania Journal of Engineering and Technology
Power System Reliability and Maintenance
article

Assessment of Maintenance Performance Level of Selected Hydropower Plants in Tanzania

Mahamudu Hussein Mtebwa, Mathew Joachim Bundala
article en

Abstract

Despite significant progress in increasing electricity access to over 78%, electricity reliability in Tanzania remains a concern, with frequent power outages reported. Maintenance issues in hydropower plants have been identified as a critical factor contributing to this problem. However, the specific maintenance performance levels have not been fully assessed. This study conducts a comprehensive evaluation of the maintenance performance of four key hydropower plants: Kidatu (204 MW), Kihansi (180 MW), Mtera (80 MW), and New Pangani Falls (68 MW). Data collected from staff surveys and maintenance records between 2018 and 2022 were used in the study. Although staff demonstrated a reasonable awareness of the hydropower plants Key Performance Indicators (KPIs), with a minimum mean score of 3.66, the findings reveal underperformance across all plants, with a heavy reliance on reactive rather than proactive maintenance. Low plant availability (89%), insufficient planned work (42%), and excessive unplanned work (55%) were recorded. High Mean time to Repair and frequent failures, particularly at New Pangani Falls, were also observed. This research underscores the importance of strategic maintenance improvements to enhance the reliability and efficiency of Tanzania's hydropower sector.

Tanzania Journal of Engineering and TechnologyVol. 44(2)
Openalex Percentile: Top 83%
Power System Reliability and Maintenance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Assessment of Maintenance Performance Level of Selected Hydropower Plants in Tanzania — Mahamudu Hussein Mtebwa, Mathew Joachim Bundala · Tanzania Journal of Engineering and Technology (2025) | TGRS Research Map | TGRS