Pekanbaru Town Square Development With Concept Mix Use Building (Shopping Mall, Hotel, Condotel, Convention, Sport Centre)

This study assesses the financial feasibility of a privately financed infrastructure project under a Build-Operate-Transfer (BOT) scheme with a total investment of USD 76 million. The investment is distributed over a three-year construction phase, followed by a 30- to 60-year operation period generating annual net profits of USD 8.64 million. Key financial metrics including Net Present Value (NPV) and Internal Rate of Return (IRR) are utilized to evaluate the project. The results indicate a negative NPV of approximately USD -14.85 million for a 30-year operation, suggesting the project is not viable under a conservative time horizon. However, extending the operation to 60 years yields a positive NPV of USD +23.8 million and an estimated IRR of 11.7%, surpassing the assumed discount rate of 10%. These findings highlight the importance of operational duration in BOT projects and suggest that long-term operation is essential to achieve financial sustainability. Recommendations include extending the concession period and optimizing cost structures to enhance investment attractiveness.

Authors

Publication Details

Journal
Journal of Civil Engineering and Planning
Published
2025-06-02
DOI
https://doi.org/10.37253/jcep.v6i1.10106
Primary Topic
Architectural and Urban Studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Pekanbaru Town Square Development With Concept Mix Use Building (Shopping Mall, Hotel, Condotel, Convention, Sport Centre)

Bambang Supeno, Muhammad Yazid, Rizki Ramadhan Husaini, Rahmat Tisnawan et al.
Journal of Civil Engineering and Planning
Architectural and Urban Studies
article

Pekanbaru Town Square Development With Concept Mix Use Building (Shopping Mall, Hotel, Condotel, Convention, Sport Centre)

Bambang Supeno, Muhammad Yazid, Rizki Ramadhan Husaini, Rahmat Tisnawan, Ahmad Kurnain
article en

Abstract

This study assesses the financial feasibility of a privately financed infrastructure project under a Build-Operate-Transfer (BOT) scheme with a total investment of USD 76 million. The investment is distributed over a three-year construction phase, followed by a 30- to 60-year operation period generating annual net profits of USD 8.64 million. Key financial metrics including Net Present Value (NPV) and Internal Rate of Return (IRR) are utilized to evaluate the project. The results indicate a negative NPV of approximately USD -14.85 million for a 30-year operation, suggesting the project is not viable under a conservative time horizon. However, extending the operation to 60 years yields a positive NPV of USD +23.8 million and an estimated IRR of 11.7%, surpassing the assumed discount rate of 10%. These findings highlight the importance of operational duration in BOT projects and suggest that long-term operation is essential to achieve financial sustainability. Recommendations include extending the concession period and optimizing cost structures to enhance investment attractiveness.

Journal of Civil Engineering and PlanningVol. 6(1)
Openalex Percentile: Top 82%
Architectural and Urban Studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Pekanbaru Town Square Development With Concept Mix Use Building (Shopping Mall, Hotel, Condotel, Convention, Sport Centre) — Bambang Supeno, Muhammad Yazid, et al. · Journal of Civil Engineering and Planning (2025) | TGRS Research Map | TGRS