Menentukan Biaya Dan Waktu Pelaksanaan Erection Konstruksi Baja Mill Building Pabrik Kelapa Sawit

This research aims to assess the costs and duration associated with the erection of steel structures in the Mill Building of PT. Tunggal Yunus Estate Palm Oil Mill, located in Kampar, Riau. The palm oil sector plays a significant role in Indonesia's economy, making the presence of Palm Oil Mills (PKS) essential for palm oil production. Utilizing a quantitative methodology with a case study approach, the study analyzes work volume, equipment and labor productivity, as well as cost and time estimations. Results reveal that the erection period for the steel structure is 40 calendar days, which corresponds with the actual time recorded on-site. The overall cost of erection is IDR 276,075,000.00, resulting in a unit cost of IDR 1,854/kg. Various factors affecting costs and duration include weather conditions, the challenging muddy terrain of the project site, and the coordination among work teams. This study offers valuable insights for the planning and budgeting of future steel construction projects within the palm oil industry.

Authors

Institutions

Publication Details

Journal
Syntax Literate Jurnal Ilmiah Indonesia
Published
2025-06-17
DOI
https://doi.org/10.36418/syntax-literate.v10i6.59942
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Menentukan Biaya Dan Waktu Pelaksanaan Erection Konstruksi Baja Mill Building Pabrik Kelapa Sawit

Mardiaman Mardiaman, Dicky Januarizky Silitonga
4 links
Syntax Literate Jurnal Ilmiah Indonesia
Management and Optimization Techniques
article

Menentukan Biaya Dan Waktu Pelaksanaan Erection Konstruksi Baja Mill Building Pabrik Kelapa Sawit

Mardiaman Mardiaman, Dicky Januarizky Silitonga
article en

Abstract

This research aims to assess the costs and duration associated with the erection of steel structures in the Mill Building of PT. Tunggal Yunus Estate Palm Oil Mill, located in Kampar, Riau. The palm oil sector plays a significant role in Indonesia's economy, making the presence of Palm Oil Mills (PKS) essential for palm oil production. Utilizing a quantitative methodology with a case study approach, the study analyzes work volume, equipment and labor productivity, as well as cost and time estimations. Results reveal that the erection period for the steel structure is 40 calendar days, which corresponds with the actual time recorded on-site. The overall cost of erection is IDR 276,075,000.00, resulting in a unit cost of IDR 1,854/kg. Various factors affecting costs and duration include weather conditions, the challenging muddy terrain of the project site, and the coordination among work teams. This study offers valuable insights for the planning and budgeting of future steel construction projects within the palm oil industry.

Syntax Literate Jurnal Ilmiah IndonesiaVol. 10(6)
Universitas Tama Jagakarsa (ID)
Openalex Percentile: Top 79%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Menentukan Biaya Dan Waktu Pelaksanaan Erection Konstruksi Baja Mill Building Pabrik Kelapa Sawit — Mardiaman Mardiaman, Dicky Januarizky Silitonga · Syntax Literate Jurnal Ilmiah Indonesia (2025) | TGRS Research Map | TGRS