Risk Analysis at The Planning Stage in The Biomethane Production Plant Construction Project: A Case Study on PT A

This study aims to identify potential risks during the planning phase of a biomethane plant construction project at PT A and to develop appropriate mitigation strategies. Using a qualitative case study approach, data were collected through interviews and questionnaires involving key personnel from the risk management and research divisions. A total of 27 risks were identified, and eight were prioritized based on their severity. Three primary mitigation strategies were applied: risk likelihood reduction, risk avoidance, and risk consequence reduction. The findings reveal that the highest priority risks include public objections, natural events, economic instability, unrealistic project durations, emerging stakeholders, scope creep, unclear contracts, and inappropriate technology selection. Each risk was addressed with tailored mitigation measures aligned with practical project management principles. For instance, enhancing community engagement, drafting clearer contracts, and involving expert consultants were among the real-world strategies implemented. The practical implications of this study are significant for project managers and stakeholders involved in similar construction projects. The structured risk analysis framework and corresponding mitigation actions can be used as a reference to anticipate challenges early and implement preventive measures effectively. This contributes to improved decision-making, reduced project delays, and strengthened project sustainability in high-risk industries like bioenergy development.

Authors

Institutions

Publication Details

Journal
Eduvest - Journal Of Universal Studies
Published
2025-06-16
DOI
https://doi.org/10.59188/eduvest.v5i6.51306
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Risk Analysis at The Planning Stage in The Biomethane Production Plant Construction Project: A Case Study on PT A

Tubagus M. Yusuf Khudri, Agnes Debora Ginting
Eduvest - Journal Of Universal Studies
Management and Optimization Techniques
article

Risk Analysis at The Planning Stage in The Biomethane Production Plant Construction Project: A Case Study on PT A

Tubagus M. Yusuf Khudri, Agnes Debora Ginting
article en

Abstract

This study aims to identify potential risks during the planning phase of a biomethane plant construction project at PT A and to develop appropriate mitigation strategies. Using a qualitative case study approach, data were collected through interviews and questionnaires involving key personnel from the risk management and research divisions. A total of 27 risks were identified, and eight were prioritized based on their severity. Three primary mitigation strategies were applied: risk likelihood reduction, risk avoidance, and risk consequence reduction. The findings reveal that the highest priority risks include public objections, natural events, economic instability, unrealistic project durations, emerging stakeholders, scope creep, unclear contracts, and inappropriate technology selection. Each risk was addressed with tailored mitigation measures aligned with practical project management principles. For instance, enhancing community engagement, drafting clearer contracts, and involving expert consultants were among the real-world strategies implemented. The practical implications of this study are significant for project managers and stakeholders involved in similar construction projects. The structured risk analysis framework and corresponding mitigation actions can be used as a reference to anticipate challenges early and implement preventive measures effectively. This contributes to improved decision-making, reduced project delays, and strengthened project sustainability in high-risk industries like bioenergy development.

Eduvest - Journal Of Universal StudiesVol. 5(6)
University of Indonesia (ID)
Openalex Percentile: Top 80%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Risk Analysis at The Planning Stage in The Biomethane Production Plant Construction Project: A Case Study on PT A — Tubagus M. Yusuf Khudri, Agnes Debora Ginting · Eduvest - Journal Of Universal Studies (2025) | TGRS Research Map | TGRS