Modeling Sustainable Earned Value Management (EVM) Under Grey Uncertain Conditions

The EVM method is an essential project management technique that compares the work done to the planned values (PVs) to identify project variances. However, the inherent uncertainties and possibilities in the project introduce uncertainty in the input data. Despite this importance, the input data for this method is often considered deterministic in most research, and several researchers have modeled it under fuzzy information. In this research, we developed a novel approach using a combined model of fuzzy numbers and grey numbers called interval grey triangular fuzzy (IGTF) numbers. This model is designed to manage the project’s fuzzy grey value, addressing the two pillars of fuzzy and grey uncertainty. The findings of the study indicate that by combining the grey degree of confidence with the triangular fuzzy number (TFN), the results are closer to the real world and more lenient. Finally, based on the estimation of the actual final cost of the project, managers are encouraged to use certainty in lowering costs concerning the value obtained by using the Z-number for the phases of the project. This research provides practical insights and a new model for managing sustainable project uncertainties using fuzzy and grey theories, offering a potential solution to this challenge.

Authors

Institutions

Publication Details

Journal
Systems
Published
2025-06-17
DOI
https://doi.org/10.3390/systems13060484
Primary Topic
Multi-Criteria Decision Making
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Modeling Sustainable Earned Value Management (EVM) Under Grey Uncertain Conditions

S. Mohammad Nejad, Morteza Bagherpour, Negar Karimi, Mohammad Reza Feylizadeh et al.
Systems
Multi-Criteria Decision Making
article

Modeling Sustainable Earned Value Management (EVM) Under Grey Uncertain Conditions

S. Mohammad Nejad, Morteza Bagherpour, Negar Karimi, Mohammad Reza Feylizadeh, Lei Fan
article en

Abstract

The EVM method is an essential project management technique that compares the work done to the planned values (PVs) to identify project variances. However, the inherent uncertainties and possibilities in the project introduce uncertainty in the input data. Despite this importance, the input data for this method is often considered deterministic in most research, and several researchers have modeled it under fuzzy information. In this research, we developed a novel approach using a combined model of fuzzy numbers and grey numbers called interval grey triangular fuzzy (IGTF) numbers. This model is designed to manage the project’s fuzzy grey value, addressing the two pillars of fuzzy and grey uncertainty. The findings of the study indicate that by combining the grey degree of confidence with the triangular fuzzy number (TFN), the results are closer to the real world and more lenient. Finally, based on the estimation of the actual final cost of the project, managers are encouraged to use certainty in lowering costs concerning the value obtained by using the Z-number for the phases of the project. This research provides practical insights and a new model for managing sustainable project uncertainties using fuzzy and grey theories, offering a potential solution to this challenge.

SystemsVol. 13(6)
Isfahan University of Technology (IR), Jiangsu University of Science and Technology (CN), Antalya Bilim University (TR), Iran University of Science and Technology (IR), University of Pretoria (ZA), Islamic Azad University of Shiraz (IR)
Openalex Percentile: Top 84%
Multi-Criteria Decision Making
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Modeling Sustainable Earned Value Management (EVM) Under Grey Uncertain Conditions — S. Mohammad Nejad, Morteza Bagherpour, et al. · Systems (2025) | TGRS Research Map | TGRS