Visualising the impact of change orders on productivity in construction projects

Change orders are common in most construction projects and include indirect costs, such as cumulative disruption costs, as well as direct costs. However, proving and quantifying damages due to changes are difficult task; in particular, estimating the lost productivity is the most difficult task. Although there are several methods to calculate the lost productivity resulting from delay and/or disruption due to changes, they have limitations in proving damages. In this respect, visualisation of impacts is a feasible method of showing and analysing the impact of change orders on productivity. This paper shows a practical process that provides a novel visualisation method to analyse and quantify the impacts of change orders on project performance. Using the proposed approach, the impact of change orders on different activities could be identified and then estimated for the productivity loss. Ultimately, the paper contributes to the body of knowledge by helping construction professionals demonstrate and quantify the impact of change orders on the schedule and productivity concurrently towards a reasonable resolution in construction claims.

Authors

Institutions

Publication Details

Journal
Proceedings of the Institution of Civil Engineers - Management Procurement and Law
Published
2025-06-16
DOI
https://doi.org/10.1680/jmapl.24.00066
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Visualising the impact of change orders on productivity in construction projects

Jae-Seob Lee
Proceedings of the Institution of Civil Engineers - Management Procurement and Law
Construction Project Management and Performance
article

Visualising the impact of change orders on productivity in construction projects

Jae-Seob Lee
article en

Abstract

Change orders are common in most construction projects and include indirect costs, such as cumulative disruption costs, as well as direct costs. However, proving and quantifying damages due to changes are difficult task; in particular, estimating the lost productivity is the most difficult task. Although there are several methods to calculate the lost productivity resulting from delay and/or disruption due to changes, they have limitations in proving damages. In this respect, visualisation of impacts is a feasible method of showing and analysing the impact of change orders on productivity. This paper shows a practical process that provides a novel visualisation method to analyse and quantify the impacts of change orders on project performance. Using the proposed approach, the impact of change orders on different activities could be identified and then estimated for the productivity loss. Ultimately, the paper contributes to the body of knowledge by helping construction professionals demonstrate and quantify the impact of change orders on the schedule and productivity concurrently towards a reasonable resolution in construction claims.

Proceedings of the Institution of Civil Engineers - Management Procurement and Law
Dongguk University (KR)
Openalex Percentile: Top 84%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Visualising the impact of change orders on productivity in construction projects — Jae-Seob Lee · Proceedings of the Institution of Civil Engineers - Management Procurement and Law (2025) | TGRS Research Map | TGRS