An Energy-Aware Flexible Job-Shop Scheduling Problem with Sequencing Flexibility and Sequence-Dependent Setup Times

The manufacturing panorama is rapidly changing to adjust to satisfy customer demands while addressing concerns over environmental impacts. Hence, this paper proposes an extension of the Flexible Job-Shop Scheduling problem. The extension allows arbitrary precedence relationships between the operations given by a directed acyclic graph. Additionally, it considers setup times that are dependent on the sequence of the jobs as well as the total energy consumption comprised of processing and idle energy. Hence, the problem consists of allocating operations to machines and sequencing them according to precedence relationships and dependent setup times. A multi-objective mixed-integer linear programming model is formulated with the objectives of makespan and total energy consumption minimization. The formulation is solved with the weighted-sum approach. A numerical experiment is performed on five small randomly generated instances to show the model’s applicability. The model allows the incorporation of real-world settings that have been studied independently.

Authors

Institutions

Publication Details

Journal
Procedia CIRP
Published
2025-01-01
DOI
https://doi.org/10.1016/j.procir.2025.02.198
Primary Topic
Scheduling and Optimization Algorithms
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

An Energy-Aware Flexible Job-Shop Scheduling Problem with Sequencing Flexibility and Sequence-Dependent Setup Times

Jessica Olivares-Aguila, Alejandro Vital-Soto
Procedia CIRP
Scheduling and Optimization Algorithms
article

An Energy-Aware Flexible Job-Shop Scheduling Problem with Sequencing Flexibility and Sequence-Dependent Setup Times

Jessica Olivares-Aguila, Alejandro Vital-Soto
article en

Abstract

The manufacturing panorama is rapidly changing to adjust to satisfy customer demands while addressing concerns over environmental impacts. Hence, this paper proposes an extension of the Flexible Job-Shop Scheduling problem. The extension allows arbitrary precedence relationships between the operations given by a directed acyclic graph. Additionally, it considers setup times that are dependent on the sequence of the jobs as well as the total energy consumption comprised of processing and idle energy. Hence, the problem consists of allocating operations to machines and sequencing them according to precedence relationships and dependent setup times. A multi-objective mixed-integer linear programming model is formulated with the objectives of makespan and total energy consumption minimization. The formulation is solved with the weighted-sum approach. A numerical experiment is performed on five small randomly generated instances to show the model’s applicability. The model allows the incorporation of real-world settings that have been studied independently.

Procedia CIRPVol. 134
Cape Breton University (CA)
National Research Council Canada
Decent work and economic growth
Openalex Percentile: Top 81%
Scheduling and Optimization Algorithms
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.