Corrosion protection challenges for Australia’s longest single-lane bridge in a harsh marine environment

The Mission River Bridge in Weipa, Queensland, is Australia’s longest single-lane bridge spanning 1040 meters. Built in 1971 with a 35-year design life, the bridge plays a key role in supporting the region’s mining operations and its local communities. Over time, its steel piles have suffered significant section loss due to Microbially Induced Corrosion (MIC) in the aggressive marine environment. To mitigate further degradation and extend the bridge’s service life, Impressed Current Cathodic Protection (ICCP) systems were installed. The composite piles, consisting of prestressed concrete in the upper section and steel in the lower section, are protected by the ICCP systems up to mid-tide level. A Mixed Metal Oxide (MMO) ribbon anode system was also installed to protect the atmospheric zones, including the piles and sections of the headstocks. This paper presents a case study on the cathodic protection systems implemented for this complex marine structure. It highlights the technical challenges posed by MIC and the harsh environmental conditions, and it critically examines the limitations of current cathodic protection standards in addressing protection criteria for similarly complex structures.

Authors

Institutions

Publication Details

Journal
MATEC Web of Conferences
Published
2025-01-01
DOI
https://doi.org/10.1051/matecconf/202540904001
Primary Topic
Concrete Corrosion and Durability
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Corrosion protection challenges for Australia’s longest single-lane bridge in a harsh marine environment

Atef Cheaitani, Bob Brown, Rhett Lamperd
MATEC Web of Conferences
Concrete Corrosion and Durability
article

Corrosion protection challenges for Australia’s longest single-lane bridge in a harsh marine environment

Atef Cheaitani, Bob Brown, Rhett Lamperd
article en

Abstract

The Mission River Bridge in Weipa, Queensland, is Australia’s longest single-lane bridge spanning 1040 meters. Built in 1971 with a 35-year design life, the bridge plays a key role in supporting the region’s mining operations and its local communities. Over time, its steel piles have suffered significant section loss due to Microbially Induced Corrosion (MIC) in the aggressive marine environment. To mitigate further degradation and extend the bridge’s service life, Impressed Current Cathodic Protection (ICCP) systems were installed. The composite piles, consisting of prestressed concrete in the upper section and steel in the lower section, are protected by the ICCP systems up to mid-tide level. A Mixed Metal Oxide (MMO) ribbon anode system was also installed to protect the atmospheric zones, including the piles and sections of the headstocks. This paper presents a case study on the cathodic protection systems implemented for this complex marine structure. It highlights the technical challenges posed by MIC and the harsh environmental conditions, and it critically examines the limitations of current cathodic protection standards in addressing protection criteria for similarly complex structures.

MATEC Web of ConferencesVol. 409
University of Technology Sydney (AU)
Openalex Percentile: Top 86%
Concrete Corrosion and Durability
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Corrosion protection challenges for Australia’s longest single-lane bridge in a harsh marine environment — Atef Cheaitani, Bob Brown, et al. · MATEC Web of Conferences (2025) | TGRS Research Map | TGRS