Ability of Technologies to Collect the Positioning and Occupancy of Work Crews and Resources on Construction Job Sites

Introduction Efficiently updating construction schedules is vital for managing dynamic workflows. Traditional methods like Gantt charts rely on manual updates, but newer approaches, such as Chronographic Modelling and Dynamic Modelling of Occupancy Rate Scheduling (DMORS), require tracking spatial positioning and occupancy rates of teams and resources. Given the complexity of these tasks, emerging technologies are being adopted to enhance data collection. Methods This study reviews recent advancements in tracking construction site occupancy and spatial positioning. It categorizes these technologies into three main types: image and video capture, 3D point cloud generation, and sensor-based tracking systems. Each method is evaluated based on seven essential criteria: data collection speed, portability, accuracy, worksite impact, post-processing time, accessibility, and technology maturity. Results The research provides a selection framework for contractors, helping them choose the most suitable tools based on project size and complexity. High-precision tools like LiDAR and laser scanning are ideal for large contractors requiring detailed modelling, while smaller firms may prefer cost-effective solutions such as manual data collection with photos or videos. Discussion This research highlights that no single technology meets all needs for tracking construction site occupancy. High-precision tools offer accuracy but may disrupt work, while simpler methods are easier to use but less detailed. So, depending on the size of the contractor or the project, the best technology may vary. Conclusion Ultimately, this paper supports the integration of space planning schedules in construction management by offering a structured approach to implementing modern data capture technologies. The study also highlights future trends, advocating for multi-technology integration to improve accuracy and exploring the potential of artificial intelligence for automated data analysis.

Authors

Institutions

Publication Details

Journal
The Open Civil Engineering Journal
Published
2025-06-13
DOI
https://doi.org/10.2174/0118741495375592250610133455
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Ability of Technologies to Collect the Positioning and Occupancy of Work Crews and Resources on Construction Job Sites

Adel Francis, Stéphane Morin Pépin
The Open Civil Engineering Journal
BIM and Construction Integration
article

Ability of Technologies to Collect the Positioning and Occupancy of Work Crews and Resources on Construction Job Sites

Adel Francis, Stéphane Morin Pépin
article en

Abstract

Introduction Efficiently updating construction schedules is vital for managing dynamic workflows. Traditional methods like Gantt charts rely on manual updates, but newer approaches, such as Chronographic Modelling and Dynamic Modelling of Occupancy Rate Scheduling (DMORS), require tracking spatial positioning and occupancy rates of teams and resources. Given the complexity of these tasks, emerging technologies are being adopted to enhance data collection. Methods This study reviews recent advancements in tracking construction site occupancy and spatial positioning. It categorizes these technologies into three main types: image and video capture, 3D point cloud generation, and sensor-based tracking systems. Each method is evaluated based on seven essential criteria: data collection speed, portability, accuracy, worksite impact, post-processing time, accessibility, and technology maturity. Results The research provides a selection framework for contractors, helping them choose the most suitable tools based on project size and complexity. High-precision tools like LiDAR and laser scanning are ideal for large contractors requiring detailed modelling, while smaller firms may prefer cost-effective solutions such as manual data collection with photos or videos. Discussion This research highlights that no single technology meets all needs for tracking construction site occupancy. High-precision tools offer accuracy but may disrupt work, while simpler methods are easier to use but less detailed. So, depending on the size of the contractor or the project, the best technology may vary. Conclusion Ultimately, this paper supports the integration of space planning schedules in construction management by offering a structured approach to implementing modern data capture technologies. The study also highlights future trends, advocating for multi-technology integration to improve accuracy and exploring the potential of artificial intelligence for automated data analysis.

The Open Civil Engineering JournalVol. 19(1)
École de Technologie Supérieure (CA)
Openalex Percentile: Top 86%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Ability of Technologies to Collect the Positioning and Occupancy of Work Crews and Resources on Construction Job Sites — Adel Francis, Stéphane Morin Pépin · The Open Civil Engineering Journal (2025) | TGRS Research Map | TGRS