PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE EARNED VALUE ANALYSIS (EVA) PADA PROYEK JARINGAN IPAL KOTA PALEMBANG

Abstract In executing a project, it is essential to maintain control to address any deviations, ensuring the project remains on schedule. Consequently, oversight and control measures must be implemented across all areas, particularly in terms of time and cost management. The Palembang City Wastewater Treatment Plant Network Project faced delays in its field operations, leading to discrepancies from the original timeline. In this context, the author will evaluate cost and time management using the Earned Value Analysis (EVA) method to assess performance and estimate the total cost and time needed for project completion, considering the delays. The EVA method serves as a comprehensive approach to manage project costs and schedules. The key parameters for this analysis are SEAC and BEAC. The SEAC indicates the projected duration necessary to complete the project, estimated at 918 days, while the BEAC reflects the total estimated cost for completion, amounting to Rp 210,078,454,167.97. The project's performance, evaluated through cost and time metrics via Earned Value Analysis, revealed unsatisfactory cost performance, as indicated by a negative CV value at the 25th month, the conclusion of the study, and a CPI of less than 1. This signifies that actual costs have exceeded planned costs, with negative SV and an SPI of less than 1, pointing to delays in the project. Keywords— Earned Value Analysis (EVA), Control, Cost, Time.

Authors

Publication Details

Journal
Jurnal Teknik Sipil dan Teknologi Konstruksi
Published
2024-10-26
DOI
https://doi.org/10.35308/jts-utu.v10i2.10511
Primary Topic
Urban Transport Systems Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE EARNED VALUE ANALYSIS (EVA) PADA PROYEK JARINGAN IPAL KOTA PALEMBANG

Muhammad Gumilar Akbar, Ely Mulyati
Jurnal Teknik Sipil dan Teknologi Konstruksi
Urban Transport Systems Analysis
article

PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE EARNED VALUE ANALYSIS (EVA) PADA PROYEK JARINGAN IPAL KOTA PALEMBANG

Muhammad Gumilar Akbar, Ely Mulyati
article en

Abstract

Abstract In executing a project, it is essential to maintain control to address any deviations, ensuring the project remains on schedule. Consequently, oversight and control measures must be implemented across all areas, particularly in terms of time and cost management. The Palembang City Wastewater Treatment Plant Network Project faced delays in its field operations, leading to discrepancies from the original timeline. In this context, the author will evaluate cost and time management using the Earned Value Analysis (EVA) method to assess performance and estimate the total cost and time needed for project completion, considering the delays. The EVA method serves as a comprehensive approach to manage project costs and schedules. The key parameters for this analysis are SEAC and BEAC. The SEAC indicates the projected duration necessary to complete the project, estimated at 918 days, while the BEAC reflects the total estimated cost for completion, amounting to Rp 210,078,454,167.97. The project's performance, evaluated through cost and time metrics via Earned Value Analysis, revealed unsatisfactory cost performance, as indicated by a negative CV value at the 25th month, the conclusion of the study, and a CPI of less than 1. This signifies that actual costs have exceeded planned costs, with negative SV and an SPI of less than 1, pointing to delays in the project. Keywords— Earned Value Analysis (EVA), Control, Cost, Time.

Jurnal Teknik Sipil dan Teknologi KonstruksiVol. 10(2)
Openalex Percentile: Top 67%
Urban Transport Systems Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

PENGENDALIAN BIAYA DAN WAKTU DENGAN METODE EARNED VALUE ANALYSIS (EVA) PADA PROYEK JARINGAN IPAL KOTA PALEMBANG — Muhammad Gumilar Akbar, Ely Mulyati · Jurnal Teknik Sipil dan Teknologi Konstruksi (2024) | TGRS Research Map | TGRS