Measuring Workers' Productivity in the Rural Infrastructure Construction Project Using the Historical Experience Method

The success of a construction project as a whole depends on the success of each job in the project, while one of the factors that influences the success of a job is the productivity of its workforce. This is because work in a construction project is labor-intensive, which means using a lot of labor, and the majority of the work is done manually. Lack of attention to worker productivity in a construction project can hinder construction work. The purpose of this study is to determine the value of worker productivity in Check Dam work using the Historical Experience method. The results of this study indicate that in the reinforcement work, the average productivity value in the field is 17.0630 kg/ hour, in the formwork 2.44 m²/ hour, in the casting work 0.30 m³/ hour, in the formwork dismantling work 5.30 m²/ hour. While the average productivity coefficient value in the field in the reinforcement work is 2.40 OH, in the formwork 0.33 OH, in the casting work 1.88 OH, and in the formwork dismantling work 0.33 OH.

Authors

Publication Details

Journal
International Journal of Civil Engineering
Published
2025-05-31
DOI
https://doi.org/10.14445/23488352/ijce-v12i5p106
Primary Topic
Korean Urban and Social Studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Measuring Workers' Productivity in the Rural Infrastructure Construction Project Using the Historical Experience Method

Nova Nevila Rodhi, Mohamad Ferdaus Noor Aulady
International Journal of Civil Engineering
Korean Urban and Social Studies
article

Measuring Workers' Productivity in the Rural Infrastructure Construction Project Using the Historical Experience Method

Nova Nevila Rodhi, Mohamad Ferdaus Noor Aulady
article en

Abstract

The success of a construction project as a whole depends on the success of each job in the project, while one of the factors that influences the success of a job is the productivity of its workforce. This is because work in a construction project is labor-intensive, which means using a lot of labor, and the majority of the work is done manually. Lack of attention to worker productivity in a construction project can hinder construction work. The purpose of this study is to determine the value of worker productivity in Check Dam work using the Historical Experience method. The results of this study indicate that in the reinforcement work, the average productivity value in the field is 17.0630 kg/ hour, in the formwork 2.44 m²/ hour, in the casting work 0.30 m³/ hour, in the formwork dismantling work 5.30 m²/ hour. While the average productivity coefficient value in the field in the reinforcement work is 2.40 OH, in the formwork 0.33 OH, in the casting work 1.88 OH, and in the formwork dismantling work 0.33 OH.

International Journal of Civil EngineeringVol. 12(5)
Decent work and economic growth
Openalex Percentile: Top 82%
Korean Urban and Social Studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.