The impact of technology, cost, time, and stakeholders on construction project management performance in iraq

Abstract— this study examines the impact of technology, cost, time, and stakeholders on construction project management performance in iraq. Using a quantitative research design, data was collected from 300 participants working in iraqi construction companies through a structured questionnaire with a likert scale. The data was analyzed using smart pls to assess the relationships between the independent variables (technology, cost, time, stakeholders) and the dependent variable (project management performance). The results show that for project performance, there is a positive effect of technology, cost management, and time management. This study highlights the contributions of such factors to increase efficiency, verifying the budget, completing the project as per a schedule time and enhancing cooperation among all parties to the construction project in iraq. The outcomes support existing literature and provide actionable recommendations for improving project management practices. Further studies on other variables and qualitative studies are recommended to confirm the results of the study. The present study adds to the literature efforts towards understanding construction project management in developing world, and particularly iraq. Keywords: construction project management, technology adoption, cost management, stakeholder engagement and project performance

Authors

Publication Details

Published
2025-05-20
DOI
https://doi.org/10.24086/icace2025/paper.1713
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

The impact of technology, cost, time, and stakeholders on construction project management performance in iraq

Azwar M. Qasim Agha, Muslim Najeeb Zaidan, Alhamza yassin flaih maeni
Construction Project Management and Performance
article

The impact of technology, cost, time, and stakeholders on construction project management performance in iraq

Azwar M. Qasim Agha, Muslim Najeeb Zaidan, Alhamza yassin flaih maeni
article en

Abstract

Abstract— this study examines the impact of technology, cost, time, and stakeholders on construction project management performance in iraq. Using a quantitative research design, data was collected from 300 participants working in iraqi construction companies through a structured questionnaire with a likert scale. The data was analyzed using smart pls to assess the relationships between the independent variables (technology, cost, time, stakeholders) and the dependent variable (project management performance). The results show that for project performance, there is a positive effect of technology, cost management, and time management. This study highlights the contributions of such factors to increase efficiency, verifying the budget, completing the project as per a schedule time and enhancing cooperation among all parties to the construction project in iraq. The outcomes support existing literature and provide actionable recommendations for improving project management practices. Further studies on other variables and qualitative studies are recommended to confirm the results of the study. The present study adds to the literature efforts towards understanding construction project management in developing world, and particularly iraq. Keywords: construction project management, technology adoption, cost management, stakeholder engagement and project performance

Openalex Percentile: Top 86%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

The impact of technology, cost, time, and stakeholders on construction project management performance in iraq — Azwar M. Qasim Agha, Muslim Najeeb Zaidan, et al. · (2025) | TGRS Research Map | TGRS