Analisis Produktivitas Dump Truck Pada Storage Alternative Fuel And Raw Material Dengan Metode Cycle Time

This research reviews the planning and implementation of alternative fuel facilities at PT. Semen Gresik Rembang Factory, with a focus on storage and transportation efficiency of alternative fuels using the cycle time calculation method. This new facility is designed to increase the efficiency and smoothness of the cement production process, especially in the use of Alternative Fuel and Raw Material (AFR). By applying cycle time calculations, the time required to transport product waste from storage to the apron belt feeder with a dump truck can be determined more precisely. The results of the research show that the time required to use product waste in storage is 12 days, with a total cycle time from storage to apron of 16.68 minutes (0.3 hours) and requires 2 dump trucks to meet the needs of the apron belt feeder in one shift. The implementation of this method is expected to expedite the production process and increase operational efficiency at the Semen Gresik Plant Rembang Factory.

Publication Details

Published
2024-11-18
DOI
https://doi.org/10.33863/cdma.v8i1.2898
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analisis Produktivitas Dump Truck Pada Storage Alternative Fuel And Raw Material Dengan Metode Cycle Time

Management and Optimization Techniques
article

Analisis Produktivitas Dump Truck Pada Storage Alternative Fuel And Raw Material Dengan Metode Cycle Time

article en

Abstract

This research reviews the planning and implementation of alternative fuel facilities at PT. Semen Gresik Rembang Factory, with a focus on storage and transportation efficiency of alternative fuels using the cycle time calculation method. This new facility is designed to increase the efficiency and smoothness of the cement production process, especially in the use of Alternative Fuel and Raw Material (AFR). By applying cycle time calculations, the time required to transport product waste from storage to the apron belt feeder with a dump truck can be determined more precisely. The results of the research show that the time required to use product waste in storage is 12 days, with a total cycle time from storage to apron of 16.68 minutes (0.3 hours) and requires 2 dump trucks to meet the needs of the apron belt feeder in one shift. The implementation of this method is expected to expedite the production process and increase operational efficiency at the Semen Gresik Plant Rembang Factory.

Openalex Percentile: Top 48%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.