Impact Analysis of BIM on Power Substation Project Costs: Techno-Economic Data Evidence from China

Due to the difficulty in measuring intangible effects and the reliance on experts for benefit evaluation, actual project data evidence of the impact of BIM is insufficient. To this end, this study collected total project cost data from 164 power substation projects and techno-economic statements from 34 power substation projects from SGCC to capture data evidence of the impact of BIM on project costs and explore its patterns. Algorithms such as hierarchical clustering based on improved DTW and feature selection based on QDA were designed for data mining. The findings demonstrate that the distribution of the CV% of total project costs and the CV% of some specific cost items became more concentrated after the application of BIM, which indicates that BIM enhanced the ability to predict and control project costs. Moreover, five cost items and five shape patterns of cost items were identified as key to the impact of BIM. It is therefore recommended that the related cost items should be controlled with focus during the application of BIM.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2025-05-29
DOI
https://doi.org/10.3390/buildings15111885
Citations
1
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
1.01

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Impact Analysis of BIM on Power Substation Project Costs: Techno-Economic Data Evidence from China

Ding Liu, Yi Sun, Jingguo Rong, Lizhong Qi et al.
1 citations
Buildings
BIM and Construction Integration
1.01
article

Impact Analysis of BIM on Power Substation Project Costs: Techno-Economic Data Evidence from China

Ding Liu, Yi Sun, Jingguo Rong, Lizhong Qi, G.J. Yu, Su Zhang
article en
1 citations

Abstract

Due to the difficulty in measuring intangible effects and the reliance on experts for benefit evaluation, actual project data evidence of the impact of BIM is insufficient. To this end, this study collected total project cost data from 164 power substation projects and techno-economic statements from 34 power substation projects from SGCC to capture data evidence of the impact of BIM on project costs and explore its patterns. Algorithms such as hierarchical clustering based on improved DTW and feature selection based on QDA were designed for data mining. The findings demonstrate that the distribution of the CV% of total project costs and the CV% of some specific cost items became more concentrated after the application of BIM, which indicates that BIM enhanced the ability to predict and control project costs. Moreover, five cost items and five shape patterns of cost items were identified as key to the impact of BIM. It is therefore recommended that the related cost items should be controlled with focus during the application of BIM.

BuildingsVol. 15(11)
North China Electric Power University (CN)
National Key Research and Development Program of China
Openalex Percentile: Top 24%
BIM and Construction Integration
1.01
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.