The calculation method of critical chain buffer based on GERT network and information entropy

In order to address project delays caused by uncertain factors in the construction project schedule management process, a new method for calculating the size of critical chain buffers is proposed. Taking into account process uncertainty and based on the GERT network, the correction process and duration of different logical processes are provided to transform the uncertain network into a deterministic one. By combining the critical chain management method and information entropy theory to assess the impact of increasing uncertainty in the merging process on the critical chain buffer, a calculation model for the critical chain buffer size based on the GERT network is established and analyzed using a numerical example. The feasibility and effectiveness of the model are verified through an example, demonstrating its ability to reduce project risks and shorten the construction period while ensuring a high probability of project completion.

Authors

Publication Details

Journal
International Journal of Industrial Engineering Computations
Published
2025-01-01
DOI
https://doi.org/10.5267/j.ijiec.2025.4.010
Citations
1
Primary Topic
Fault Detection and Control Systems
Type
article
Field-Weighted Citation Impact
1.21

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

The calculation method of critical chain buffer based on GERT network and information entropy

Qikai Li, J. Gu, Zhiyong Li, Xiangtian Nie et al.
1 citations
International Journal of Industrial Engineering Computations
Fault Detection and Control Systems
1.21
article

The calculation method of critical chain buffer based on GERT network and information entropy

Qikai Li, J. Gu, Zhiyong Li, Xiangtian Nie, Pengyuan Li
article en
1 citations

Abstract

In order to address project delays caused by uncertain factors in the construction project schedule management process, a new method for calculating the size of critical chain buffers is proposed. Taking into account process uncertainty and based on the GERT network, the correction process and duration of different logical processes are provided to transform the uncertain network into a deterministic one. By combining the critical chain management method and information entropy theory to assess the impact of increasing uncertainty in the merging process on the critical chain buffer, a calculation model for the critical chain buffer size based on the GERT network is established and analyzed using a numerical example. The feasibility and effectiveness of the model are verified through an example, demonstrating its ability to reduce project risks and shorten the construction period while ensuring a high probability of project completion.

International Journal of Industrial Engineering ComputationsVol. 16(3)
National Natural Science Foundation of China
Openalex Percentile: Top 21%
Fault Detection and Control Systems
1.21
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.