Commissioning progress of the first cryoplant for SHINE accelerator

Abstract This paper presents the commissioning progress of the first accelerator cryoplant for Shanghai high repetition rate x-ray free electron laser and extreme light facility (SHINE). To fulfil the cooling needs for the superconducting cavities in the SHINE accelerator, three cryogenic plants were contracted to Air Liquide Advanced Technologies (ALAT) in 2020. Each cryoplant could provide 4 kW cooling power at 2 K and mainly consists of a warm compressor station (WCS), a 4.5 K cold box, and a 2 K cold box. Following the success delivery and installation, the WCS had been commissioned and the final 100 hours test were achieved at the middle of 2023. Afterwards, the commissioning of the 4.5 K cold box progressed as expected and the first drop of liquid helium was obtained at the end of 2023. The 2 K cold box commissioning were enabled when the installation of the cryogenic transfer line in between had been finished. At the beginning of 2024, the cold compressor had been successfully tested to achieve the 2 K super-fluid inside the 2 K cold box. The promising commissioning progress of the first cryoplant demonstrates the capability to deliver cryogenic cooling to the SHINE accelerator that are being constructed.

Authors

Institutions

Publication Details

Journal
IOP Conference Series Materials Science and Engineering
Published
2025-05-01
DOI
https://doi.org/10.1088/1757-899x/1327/1/012024
Primary Topic
Particle accelerators and beam dynamics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Commissioning progress of the first cryoplant for SHINE accelerator

Dafei Wang, Shuai Zhang, Pengfei Zhang, Yan Zhang et al.
IOP Conference Series Materials Science and Engineering
Particle accelerators and beam dynamics
article

Commissioning progress of the first cryoplant for SHINE accelerator

Dafei Wang, Shuai Zhang, Pengfei Zhang, Yan Zhang, Shuwei Zhang, Jiuce Sun, Zhengrong Ouyang
article en

Abstract

Abstract This paper presents the commissioning progress of the first accelerator cryoplant for Shanghai high repetition rate x-ray free electron laser and extreme light facility (SHINE). To fulfil the cooling needs for the superconducting cavities in the SHINE accelerator, three cryogenic plants were contracted to Air Liquide Advanced Technologies (ALAT) in 2020. Each cryoplant could provide 4 kW cooling power at 2 K and mainly consists of a warm compressor station (WCS), a 4.5 K cold box, and a 2 K cold box. Following the success delivery and installation, the WCS had been commissioned and the final 100 hours test were achieved at the middle of 2023. Afterwards, the commissioning of the 4.5 K cold box progressed as expected and the first drop of liquid helium was obtained at the end of 2023. The 2 K cold box commissioning were enabled when the installation of the cryogenic transfer line in between had been finished. At the beginning of 2024, the cold compressor had been successfully tested to achieve the 2 K super-fluid inside the 2 K cold box. The promising commissioning progress of the first cryoplant demonstrates the capability to deliver cryogenic cooling to the SHINE accelerator that are being constructed.

IOP Conference Series Materials Science and EngineeringVol. 1327(1)
ShanghaiTech University (CN), Shanghai Advanced Research Institute (CN)
Openalex Percentile: Top 76%
Particle accelerators and beam dynamics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Commissioning progress of the first cryoplant for SHINE accelerator — Dafei Wang, Shuai Zhang, et al. · IOP Conference Series Materials Science and Engineering (2025) | TGRS Research Map | TGRS