IMPACT OF LEAN CONSTRUCTION IMPLEMENTATION ON CONSTRUCTION BUILDING PROJECTS

Enhancing efficiency, minimizing waste, and improving project productivity are key objectives in Lean Construction. This study explores the impact of Lean Construction implementation at PT PP by examining the correlation between Planned Percentage Complete (PPC) in the Last Planner System (LPS) and project performance, including productivity and cost efficiency. The research employs a descriptive statistical analysis method, with data collected through a self-assessment survey and an evaluation of the correlation between PPC and key project management factors. The results indicate that LPS implementation significantly enhances productivity, with a positive correlation between PPC values and project efficiency. Furthermore, waste analysis reveals that Waiting, Defect, and Overproduction are construction projects' most dominant waste categories. This study also identifies that Lookahead Planning within LPS is crucial in reducing constraints, positively impacting project timeliness and cost control. Consequently, the findings provide deeper insights into Lean Construction implementation and offer strategic recommendations for companies to sustainably enhance efficiency and project performance.

Authors

Institutions

Publication Details

Journal
Jurnal PenSil
Published
2025-05-30
DOI
https://doi.org/10.21009/jpensil.v14i2.54389
Primary Topic
Quality and Management Systems
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

IMPACT OF LEAN CONSTRUCTION IMPLEMENTATION ON CONSTRUCTION BUILDING PROJECTS

Abdhy Gazali, Muhammad Sapto Nugroho, Aldy Riza Dhiandra, Alfandi Ziqri et al.
Jurnal PenSil
Quality and Management Systems
article

IMPACT OF LEAN CONSTRUCTION IMPLEMENTATION ON CONSTRUCTION BUILDING PROJECTS

Abdhy Gazali, Muhammad Sapto Nugroho, Aldy Riza Dhiandra, Alfandi Ziqri, Lintang Tirta Sari
article en

Abstract

Enhancing efficiency, minimizing waste, and improving project productivity are key objectives in Lean Construction. This study explores the impact of Lean Construction implementation at PT PP by examining the correlation between Planned Percentage Complete (PPC) in the Last Planner System (LPS) and project performance, including productivity and cost efficiency. The research employs a descriptive statistical analysis method, with data collected through a self-assessment survey and an evaluation of the correlation between PPC and key project management factors. The results indicate that LPS implementation significantly enhances productivity, with a positive correlation between PPC values and project efficiency. Furthermore, waste analysis reveals that Waiting, Defect, and Overproduction are construction projects' most dominant waste categories. This study also identifies that Lookahead Planning within LPS is crucial in reducing constraints, positively impacting project timeliness and cost control. Consequently, the findings provide deeper insights into Lean Construction implementation and offer strategic recommendations for companies to sustainably enhance efficiency and project performance.

Jurnal PenSilVol. 14(2)
Universitas Trisakti (ID), State University of Jakarta (ID), Delft University of Technology (NL)
Openalex Percentile: Top 82%
Quality and Management Systems
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.