Research on the Management Strategy and Quality Duration Impact of Asphalt Pavement Construction under Multi Face Handover

本文针对多工作面交接下沥青摊铺施工中存在的质量参差不齐、交付时间不一致等难题,依托上海G228公路工程,通过对比试验段1 (传统管理模式)与试验段2 (精细化协调管理模式)的施工效果,系统分析了不同组织方案和技术手段对质量、工期及成本的影响。研究表明:试验段2通过全面检查与精细预处理、接缝搭接工艺优化及高效协调管理机制,显著提升了施工质量,其压实度为98.6%、裂缝密度为3条/km、缩短工期延误至2天,并降低全生命周期成本约30%。雷达图对比显示,试验段2在施工质量、资源利用率、沟通效率及长期性能等多维度全面优于试验段1,验证了精细化管理和协同机制在复杂多工作面工程中的核心作用。为本次工程提供了可复制的管理策略与技术优化路径,为道路工程高质量建设提供技术支撑。This article focuses on the problems of uneven quality and inconsistent delivery time in asphalt pavement construction under multi face handover. Based on the Shanghai G228 highway project, by comparing the construction effects of Test Section 1 (traditional management mode) and Test Section 2 (refined coordination management mode), the impact of different organizational schemes and technical means on quality, schedule, and cost is systematically analyzed. Research has shown that Experiment Section 2 significantly improved construction quality through comprehensive inspection and fine pretreatment, optimization of joint overlap technology, and efficient coordination management mechanism. Its compaction degree was 98.6%, crack density was 3 cracks/km, construction period delay was shortened to 2 days, and the total life cycle cost was reduced by about 30%. Radar chart comparison shows that test section 2 outperforms test section 1 in multiple dimensions such as construction quality, resource utilization, communication efficiency, and long-term performance, verifying the core role of refined management and collaborative mechanisms in complex multi face engineering. Provided replicable management strategies and technical optimization paths for this project, and provided technical support for high-quality construction of road engineering.

Authors

Publication Details

Journal
Hans Journal of Civil Engineering
Published
2025-01-01
DOI
https://doi.org/10.12677/hjce.2025.145121
Primary Topic
Medical Research and Treatments
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Research on the Management Strategy and Quality Duration Impact of Asphalt Pavement Construction under Multi Face Handover

剑峰 曹
Hans Journal of Civil Engineering
Medical Research and Treatments
article

Research on the Management Strategy and Quality Duration Impact of Asphalt Pavement Construction under Multi Face Handover

剑峰 曹
article en

Abstract

本文针对多工作面交接下沥青摊铺施工中存在的质量参差不齐、交付时间不一致等难题,依托上海G228公路工程,通过对比试验段1 (传统管理模式)与试验段2 (精细化协调管理模式)的施工效果,系统分析了不同组织方案和技术手段对质量、工期及成本的影响。研究表明:试验段2通过全面检查与精细预处理、接缝搭接工艺优化及高效协调管理机制,显著提升了施工质量,其压实度为98.6%、裂缝密度为3条/km、缩短工期延误至2天,并降低全生命周期成本约30%。雷达图对比显示,试验段2在施工质量、资源利用率、沟通效率及长期性能等多维度全面优于试验段1,验证了精细化管理和协同机制在复杂多工作面工程中的核心作用。为本次工程提供了可复制的管理策略与技术优化路径,为道路工程高质量建设提供技术支撑。This article focuses on the problems of uneven quality and inconsistent delivery time in asphalt pavement construction under multi face handover. Based on the Shanghai G228 highway project, by comparing the construction effects of Test Section 1 (traditional management mode) and Test Section 2 (refined coordination management mode), the impact of different organizational schemes and technical means on quality, schedule, and cost is systematically analyzed. Research has shown that Experiment Section 2 significantly improved construction quality through comprehensive inspection and fine pretreatment, optimization of joint overlap technology, and efficient coordination management mechanism. Its compaction degree was 98.6%, crack density was 3 cracks/km, construction period delay was shortened to 2 days, and the total life cycle cost was reduced by about 30%. Radar chart comparison shows that test section 2 outperforms test section 1 in multiple dimensions such as construction quality, resource utilization, communication efficiency, and long-term performance, verifying the core role of refined management and collaborative mechanisms in complex multi face engineering. Provided replicable management strategies and technical optimization paths for this project, and provided technical support for high-quality construction of road engineering.

Hans Journal of Civil EngineeringVol. 14(05)
Sustainable cities and communities
Openalex Percentile: Top 81%
Medical Research and Treatments
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.