Optimizing stochastic multi-project scheduling with a simulation integrated multi-objective genetic algorithm

The significance of project scheduling and sequencing has increased considerably in recent years, driven by the rising customer demand for highly personalized solutions. Companies have to consider multiple criteria while executing multiple projects simultaneously to meet the customer demands. Therefore, this study focuses on the multi-objective multi-project scheduling and sequencing problem (MP-SSP). A simulation-based mathematical model is developed and integrated with a multi-objective genetic algorithm. The objectives of this model are to minimize the project execution cost, project completion time and project lateness simultaneously while maximizing the resource utilization in the stochastic environment. Goal attainment programming is introduced in the simulation integrated multi-objective genetic algorithm (SIHMO-GA) to increase the effectiveness of the algorithm. Further, response surface methodology (RSM) has been used to find the optimum parameters of the proposed SIHMO-GA. The effectiveness of the proposed SIHMO-GA is evaluated through a real-world case study by comparing it with simulation-optimization approaches, namely the multi-objective genetic algorithm (MOGA) and goal attainment programming. Gap analysis indicates that the SIHMO-GA provides best trade off values of the above-mentioned conflicting objectives under a stochastic environment. This study supports practical scheduling and sequencing of multiple projects in a stochastic environment by generating solutions that maximize profit, enhance resource utilization, and ensure customer satisfaction through timely project delivery.

Authors

Publication Details

Journal
Journal of Project Management
Published
2025-01-01
DOI
https://doi.org/10.5267/j.jpm.2025.5.001
Citations
1
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
2.11
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Optimizing stochastic multi-project scheduling with a simulation integrated multi-objective genetic algorithm

Jabir Mumtaz, Mudassar Rauf, Muhammad Imran, Sana Javed
1 citations
Journal of Project Management
Resource-Constrained Project Scheduling
2.11
article

Optimizing stochastic multi-project scheduling with a simulation integrated multi-objective genetic algorithm

Jabir Mumtaz, Mudassar Rauf, Muhammad Imran, Sana Javed
article en
1 citations

Abstract

The significance of project scheduling and sequencing has increased considerably in recent years, driven by the rising customer demand for highly personalized solutions. Companies have to consider multiple criteria while executing multiple projects simultaneously to meet the customer demands. Therefore, this study focuses on the multi-objective multi-project scheduling and sequencing problem (MP-SSP). A simulation-based mathematical model is developed and integrated with a multi-objective genetic algorithm. The objectives of this model are to minimize the project execution cost, project completion time and project lateness simultaneously while maximizing the resource utilization in the stochastic environment. Goal attainment programming is introduced in the simulation integrated multi-objective genetic algorithm (SIHMO-GA) to increase the effectiveness of the algorithm. Further, response surface methodology (RSM) has been used to find the optimum parameters of the proposed SIHMO-GA. The effectiveness of the proposed SIHMO-GA is evaluated through a real-world case study by comparing it with simulation-optimization approaches, namely the multi-objective genetic algorithm (MOGA) and goal attainment programming. Gap analysis indicates that the SIHMO-GA provides best trade off values of the above-mentioned conflicting objectives under a stochastic environment. This study supports practical scheduling and sequencing of multiple projects in a stochastic environment by generating solutions that maximize profit, enhance resource utilization, and ensure customer satisfaction through timely project delivery.

Journal of Project ManagementVol. 10(3)
Openalex Percentile: Top 13%
Resource-Constrained Project Scheduling
2.11
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.