A Constrained Planning Method: Considering Storage Space Limitations and Soft Logic for Cruise Cabin Assembly Scheduling

The scheduling issues of repetitive projects such as high-rise buildings and houses have always focused on the research of project duration, costs, and personnel, while the temporary storage and transportation issues at construction sites are often overlooked. The cruise cabin assembly project exemplifies a repetitive project characterized by limited construction space. In such projects, when the process is amenable to soft logic, the construction sequences of subprocesses across all units can be modified without restriction, and various processes may be conducted concurrently, provided that the requisite resource conditions are satisfied. This paper introduces a flexible repetitive scheduling model, designated as CP-SLCRSOM, which incorporates storage space limitations and soft logic into the time-cost trade-off of the cruise cabin assembly project. This model, while thoroughly considering critical resource constraints such as material storage capacity and workforce allocation, facilitates the parallel execution of processes across different units and employs constraint programming to identify optimal or feasible solutions. The model’s efficacy is substantiated through case studies and comparisons with solutions derived from mixed-integer linear programming models.

Authors

Institutions

Publication Details

Journal
Journal of Construction Engineering and Management
Published
2025-05-29
DOI
https://doi.org/10.1061/jcemd4.coeng-16431
Primary Topic
Advanced Manufacturing and Logistics Optimization
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A Constrained Planning Method: Considering Storage Space Limitations and Soft Logic for Cruise Cabin Assembly Scheduling

Dening Song, Boxin Yang, Jinghua Li, Wenhao Huang et al.
Journal of Construction Engineering and Management
Advanced Manufacturing and Logistics Optimization
article

A Constrained Planning Method: Considering Storage Space Limitations and Soft Logic for Cruise Cabin Assembly Scheduling

Dening Song, Boxin Yang, Jinghua Li, Wenhao Huang, Lei Zhou
article en

Abstract

The scheduling issues of repetitive projects such as high-rise buildings and houses have always focused on the research of project duration, costs, and personnel, while the temporary storage and transportation issues at construction sites are often overlooked. The cruise cabin assembly project exemplifies a repetitive project characterized by limited construction space. In such projects, when the process is amenable to soft logic, the construction sequences of subprocesses across all units can be modified without restriction, and various processes may be conducted concurrently, provided that the requisite resource conditions are satisfied. This paper introduces a flexible repetitive scheduling model, designated as CP-SLCRSOM, which incorporates storage space limitations and soft logic into the time-cost trade-off of the cruise cabin assembly project. This model, while thoroughly considering critical resource constraints such as material storage capacity and workforce allocation, facilitates the parallel execution of processes across different units and employs constraint programming to identify optimal or feasible solutions. The model’s efficacy is substantiated through case studies and comparisons with solutions derived from mixed-integer linear programming models.

Journal of Construction Engineering and ManagementVol. 151(8)
Harbin University (CN), Harbin Engineering University (CN)
Affordable and clean energy
Openalex Percentile: Top 84%
Advanced Manufacturing and Logistics Optimization
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

A Constrained Planning Method: Considering Storage Space Limitations and Soft Logic for Cruise Cabin Assembly Scheduling — Dening Song, Boxin Yang, et al. · Journal of Construction Engineering and Management (2025) | TGRS Research Map | TGRS