A Study on the Differentiated Application of a Generic Scheme for Main Wiring Based on the Whole Life Cycle

Based on the theory of life cycle cost (LCC), the economic, safety and social benefits of 110kV outdoor HGIS and GIS substation are comprehensively evaluated in order to optimise the selection decision of power distribution equipment. The LCC mathematical model is constructed, and the whole life cycle cost (LCC) of the two options is quantitatively measured and comparatively analysed in terms of initial investment, operation, maintenance, failure and decommissioning disposal. The results show that the initial investment cost of the HGIS scheme is slightly higher than that of the GIS, but its operation cost is basically the same, the maintenance and fault repair cost is significantly lower than that of the GIS, and the decommissioning cost is also more advantageous. Within 40 years of operation, the whole life cycle cost of the HGIS scheme is lower than that of the GIS scheme by about 3 million RMB, which shows a better economic performance. The study shows that the application of LCC calculation method in the optimisation of general design scheme of power distribution equipment is of great value, which can provide a scientific basis for the economic decision-making of electric power engineering projects, improve the investment efficiency and operation efficiency of power grid construction, and promote the sustainable development of the industry.

Authors

Institutions

Publication Details

Published
2025-03-21
DOI
https://doi.org/10.1109/sgai64825.2025.11009822
Primary Topic
Engineering Applied Research
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A Study on the Differentiated Application of a Generic Scheme for Main Wiring Based on the Whole Life Cycle

Zhuoming Deng, Wei Lü, Xin Zhou, Qian Ma et al.
Engineering Applied Research
article

A Study on the Differentiated Application of a Generic Scheme for Main Wiring Based on the Whole Life Cycle

Zhuoming Deng, Wei Lü, Xin Zhou, Qian Ma, Xinyi Yang
article en

Abstract

Based on the theory of life cycle cost (LCC), the economic, safety and social benefits of 110kV outdoor HGIS and GIS substation are comprehensively evaluated in order to optimise the selection decision of power distribution equipment. The LCC mathematical model is constructed, and the whole life cycle cost (LCC) of the two options is quantitatively measured and comparatively analysed in terms of initial investment, operation, maintenance, failure and decommissioning disposal. The results show that the initial investment cost of the HGIS scheme is slightly higher than that of the GIS, but its operation cost is basically the same, the maintenance and fault repair cost is significantly lower than that of the GIS, and the decommissioning cost is also more advantageous. Within 40 years of operation, the whole life cycle cost of the HGIS scheme is lower than that of the GIS scheme by about 3 million RMB, which shows a better economic performance. The study shows that the application of LCC calculation method in the optimisation of general design scheme of power distribution equipment is of great value, which can provide a scientific basis for the economic decision-making of electric power engineering projects, improve the investment efficiency and operation efficiency of power grid construction, and promote the sustainable development of the industry.

China Southern Power Grid (China) (CN)
Zero hunger, Responsible consumption and production
Openalex Percentile: Top 88%
Engineering Applied Research
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.