Optimization of Profitability Based on Using Percentage of Total Float in the Project Implementation Schedule

A construction project can run well if they have efficiency in terms of time, cost and, resources. This research aims to determine optimization of the percentage of total float use to optimize project profitability, by looking at the highest Net Present Value (NPV), Return on Investment (ROI), and Benefit Cost Ratio (BCR) with a case study of the construction of a 12-story building in Surabaya. The variations used in this study include Total Float values ​​of 0%, 25%, 50%, 75%, and 100%. Based on each variation, it will produce different work weights and payment terms which will then be used for financial analysis to calculate BCR, ROI, and NPV on each cash flow to assess the optimization of the use of total float in this study. From the results of the discussion, known that most optimal cash flow planning is in scheduling conditions with the utilization of a total float value of 75% with an NPV value of Rp 7,037,643,148. with a BCR value of 1,09228 and an ROI value of 9,228%.

Authors

Publication Details

Journal
Briliant Jurnal Riset dan Konseptual
Published
2025-05-06
DOI
https://doi.org/10.28926/briliant.v10i2.2239
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Optimization of Profitability Based on Using Percentage of Total Float in the Project Implementation Schedule

I Nyoman Dita Pahang Putra, Syahril Nur Khusna Afif
Briliant Jurnal Riset dan Konseptual
Resource-Constrained Project Scheduling
article

Optimization of Profitability Based on Using Percentage of Total Float in the Project Implementation Schedule

I Nyoman Dita Pahang Putra, Syahril Nur Khusna Afif
article en

Abstract

A construction project can run well if they have efficiency in terms of time, cost and, resources. This research aims to determine optimization of the percentage of total float use to optimize project profitability, by looking at the highest Net Present Value (NPV), Return on Investment (ROI), and Benefit Cost Ratio (BCR) with a case study of the construction of a 12-story building in Surabaya. The variations used in this study include Total Float values ​​of 0%, 25%, 50%, 75%, and 100%. Based on each variation, it will produce different work weights and payment terms which will then be used for financial analysis to calculate BCR, ROI, and NPV on each cash flow to assess the optimization of the use of total float in this study. From the results of the discussion, known that most optimal cash flow planning is in scheduling conditions with the utilization of a total float value of 75% with an NPV value of Rp 7,037,643,148. with a BCR value of 1,09228 and an ROI value of 9,228%.

Briliant Jurnal Riset dan KonseptualVol. 10(2)
Openalex Percentile: Top 86%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Optimization of Profitability Based on Using Percentage of Total Float in the Project Implementation Schedule — I Nyoman Dita Pahang Putra, Syahril Nur Khusna Afif · Briliant Jurnal Riset dan Konseptual (2025) | TGRS Research Map | TGRS