Research and Application of "Catwalk First, Saddles Later" Construction Technology for Long-Span Suspension Bridges in Mountainous Areas

Construction schedule management is a pivotal factor in engineering projects, where a well-structured timeline is decisive for ensuring the on-time completion and final acceptance of the project. In the construction process of suspension bridges, the installation of tower saddles typically employs a gantry lifting system. Conventional construction practices follow a sequential workflow where the main tower saddles are installed first, followed by the construction of the catwalks. However, the production cycle for suspension bridge saddles is relatively lengthy. Delays in saddle production or supply during the construction phase can directly impede the progress of subsequent critical processes, such as catwalk installation and main cable erection, thereby severely constraining the overall project timeline. To address this issue, this paper, drawing on a specific engineering case study, proposes an innovative construction technique aimed at providing more reliable technical support and practical insights for the construction of suspension bridges.

Authors

Publication Details

Journal
Journal of civil and transportation engineering.
Published
2025-03-01
DOI
https://doi.org/10.62517/jcte.202506108
Primary Topic
Structural Engineering and Vibration Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Research and Application of "Catwalk First, Saddles Later" Construction Technology for Long-Span Suspension Bridges in Mountainous Areas

Fan Langbo, Pu Shuang, Huang Chuanteng, Han Dun
Journal of civil and transportation engineering.
Structural Engineering and Vibration Analysis
article

Research and Application of "Catwalk First, Saddles Later" Construction Technology for Long-Span Suspension Bridges in Mountainous Areas

Fan Langbo, Pu Shuang, Huang Chuanteng, Han Dun
article en

Abstract

Construction schedule management is a pivotal factor in engineering projects, where a well-structured timeline is decisive for ensuring the on-time completion and final acceptance of the project. In the construction process of suspension bridges, the installation of tower saddles typically employs a gantry lifting system. Conventional construction practices follow a sequential workflow where the main tower saddles are installed first, followed by the construction of the catwalks. However, the production cycle for suspension bridge saddles is relatively lengthy. Delays in saddle production or supply during the construction phase can directly impede the progress of subsequent critical processes, such as catwalk installation and main cable erection, thereby severely constraining the overall project timeline. To address this issue, this paper, drawing on a specific engineering case study, proposes an innovative construction technique aimed at providing more reliable technical support and practical insights for the construction of suspension bridges.

Journal of civil and transportation engineering.Vol. 2(1)
Openalex Percentile: Top 88%
Structural Engineering and Vibration Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.