Analisa Percepatan Dengan Metode Time Cost Trade Off Pada Proyek Pembangunan SPBI 2 × 200 Kl

The SPBI 2×200 KL construction project, initially planned to be completed in 360 days, experienced significant delays in the 21st week, with a progress deviation of -16.434%. To address this issue, the Time Cost Trade Off (TCTO) acceleration method was implemented by adding 4 hours of overtime work per day. This strategy successfully shortened the project duration from 336 days to 231 days, reducing the total project time by 37%. The acceleration efforts were focused on critical paths that influenced the project's completion. Although there was a 17.1% increase in direct costs due to overtime wages, additional labor, and extra materials, the application of TCTO effectively reduced indirect costs associated with prolonged project duration, such as administrative and operational expenses. Overall, this method proved to be effective in bringing the project back on schedule and preventing further losses due to delays.

Authors

Institutions

Publication Details

Journal
Sultra Civil Engineering Journal
Published
2025-04-22
DOI
https://doi.org/10.54297/sciej.v6i1.927
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analisa Percepatan Dengan Metode Time Cost Trade Off Pada Proyek Pembangunan SPBI 2 × 200 Kl

Sakinah Sakinah, Ely Mazpar, Ely Mulyati
Sultra Civil Engineering Journal
Management and Optimization Techniques
article

Analisa Percepatan Dengan Metode Time Cost Trade Off Pada Proyek Pembangunan SPBI 2 × 200 Kl

Sakinah Sakinah, Ely Mazpar, Ely Mulyati
article en

Abstract

The SPBI 2×200 KL construction project, initially planned to be completed in 360 days, experienced significant delays in the 21st week, with a progress deviation of -16.434%. To address this issue, the Time Cost Trade Off (TCTO) acceleration method was implemented by adding 4 hours of overtime work per day. This strategy successfully shortened the project duration from 336 days to 231 days, reducing the total project time by 37%. The acceleration efforts were focused on critical paths that influenced the project's completion. Although there was a 17.1% increase in direct costs due to overtime wages, additional labor, and extra materials, the application of TCTO effectively reduced indirect costs associated with prolonged project duration, such as administrative and operational expenses. Overall, this method proved to be effective in bringing the project back on schedule and preventing further losses due to delays.

Sultra Civil Engineering JournalVol. 6(1)
Universitas Bina Darma (ID)
Openalex Percentile: Top 84%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.