Implementation of Nawaz, Enscore, and Ham (NEH) for Minimize Makespan in Job Shop Scheduling

OPQ is a company that specializes in providing construction materials such as ready-mix concrete, precast concrete, concrete bricks and crushed stone. With 4 different compositions and high demand, it is not uncommon for problems to occur, namely late delivery. This research aims to increase work efficiency by minimizing makespan to reduce idle time which will impact delays in product delivery to customers. The results of production scheduling using the NEH method produce smaller makespan results and faster production process completion times compared to the scheduling method used by the company. The NEH method produces a makespan of 2.29 with the job sequence P3-P4-P2-P1. The method used by the company obtained a makespan of 3.01 with a partial work sequence of P2-P3-P4-P1. This can prove that the calculation results using the NEH method can minimize makespan and this method can be used by companies as a reference for scheduling the production process to overcome the problems being faced by the company.

Authors

Institutions

Publication Details

Journal
International Journal on Orange Technologies
Published
2025-05-17
DOI
https://doi.org/10.31149/ijot.v7i2.5438
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Implementation of Nawaz, Enscore, and Ham (NEH) for Minimize Makespan in Job Shop Scheduling

Tedjo Sukmono, Octavia Adistyas Nastiti
International Journal on Orange Technologies
Management and Optimization Techniques
article

Implementation of Nawaz, Enscore, and Ham (NEH) for Minimize Makespan in Job Shop Scheduling

Tedjo Sukmono, Octavia Adistyas Nastiti
article en

Abstract

OPQ is a company that specializes in providing construction materials such as ready-mix concrete, precast concrete, concrete bricks and crushed stone. With 4 different compositions and high demand, it is not uncommon for problems to occur, namely late delivery. This research aims to increase work efficiency by minimizing makespan to reduce idle time which will impact delays in product delivery to customers. The results of production scheduling using the NEH method produce smaller makespan results and faster production process completion times compared to the scheduling method used by the company. The NEH method produces a makespan of 2.29 with the job sequence P3-P4-P2-P1. The method used by the company obtained a makespan of 3.01 with a partial work sequence of P2-P3-P4-P1. This can prove that the calculation results using the NEH method can minimize makespan and this method can be used by companies as a reference for scheduling the production process to overcome the problems being faced by the company.

International Journal on Orange TechnologiesVol. 7(2)
Universitas Muhammadiyah Sidoarjo (ID)
Openalex Percentile: Top 84%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.