Rapid Project Delivery through Bricolage and Planning: A Case Study of the Huoshenshan Hospital Project

In recent years, the increase in major crises has highlighted the urgent need to initiate and swiftly complete emergency construction projects to mitigate their impact. However, the challenge of rapidly delivering these projects with limited resources remains underexplored. This research examines how construction projects can effectively respond to crises by applying bricolage theory in conjunction with rough planning. Using the Huoshenshan Hospital construction during the COVID-19 pandemic as a case study, this study introduces a cohesive theoretical model specifically designed for the rapid delivery of emergency construction projects. The model demonstrates how construction projects can achieve quick completion during crises by integrating two methods—rough planning and bricolage—which interact during three key stages of a project: initiation, daily routines, and significant changes. By developing this theoretical model and exploring the interactions between rough planning and bricolage to enhance resource efficiency, this study enriches the research on the rapid delivery of emergency construction projects and contributes to the crisis management literature.

Authors

Institutions

Publication Details

Journal
Journal of Construction Engineering and Management
Published
2025-05-20
DOI
https://doi.org/10.1061/jcemd4.coeng-15066
Citations
1
Primary Topic
Innovation and Knowledge Management
Type
article
Field-Weighted Citation Impact
2.23
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Rapid Project Delivery through Bricolage and Planning: A Case Study of the Huoshenshan Hospital Project

Wenchi Ying, Xin Dai, Wenxin Shen
1 citations
Journal of Construction Engineering and Management
Innovation and Knowledge Management
2.23
article

Rapid Project Delivery through Bricolage and Planning: A Case Study of the Huoshenshan Hospital Project

Wenchi Ying, Xin Dai, Wenxin Shen
article en
1 citations

Abstract

In recent years, the increase in major crises has highlighted the urgent need to initiate and swiftly complete emergency construction projects to mitigate their impact. However, the challenge of rapidly delivering these projects with limited resources remains underexplored. This research examines how construction projects can effectively respond to crises by applying bricolage theory in conjunction with rough planning. Using the Huoshenshan Hospital construction during the COVID-19 pandemic as a case study, this study introduces a cohesive theoretical model specifically designed for the rapid delivery of emergency construction projects. The model demonstrates how construction projects can achieve quick completion during crises by integrating two methods—rough planning and bricolage—which interact during three key stages of a project: initiation, daily routines, and significant changes. By developing this theoretical model and exploring the interactions between rough planning and bricolage to enhance resource efficiency, this study enriches the research on the rapid delivery of emergency construction projects and contributes to the crisis management literature.

Journal of Construction Engineering and ManagementVol. 151(8)
Beijing Jiaotong University (CN), Huazhong University of Science and Technology (CN)
Openalex Percentile: Top 12%
Innovation and Knowledge Management
2.23
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.