Network analysis-enhanced project risk management for nuclear power plant construction

• A network-based framework to model risks and their interactions in NPP projects • Topological metrics uncover critical risks neglected by classical analysis • Bi-objective project schedule optimization provides alternatives for diverse risk attitudes • A case study for the project of a DC-PWR This paper introduces a comprehensive framework for managing interdependent delay risks in nuclear power plant (NPP) construction by integrating network theory and topological analysis. Spent fuel disposal, nuclear plant safety and nuclear weapons proliferation are known important concerns for nuclear power development, but costs remain the fundamental problem, as NPP projects are plagued by schedule delays that substantially increase total costs. Such complex megaprojects are exposed to numerous risks of different sources that behave interdependently. Most of the studies understand the risks of delay in NPP construction projects in isolation without taking interdependencies into account. The proposed methodology employs a Design Structure Matrix (DSM) to construct a Risk Interaction Network (RIN), enabling a topological assessment to identify critical risks that may cause cascading delays in project tasks. An algorithmic search for these critical risks is conducted, considering the impact of their removal on the RIN's characteristics. We define a bi-objective optimization problem aimed at generating a project schedule that minimizes both the project's makespan and the reachability density of the RIN. The solution is obtained using an evolutionary algorithm. Applied to a Double-Containment Pressurized Water Reactor (DC-PWR) project, this approach effectively uncovers risks neglected by classical analysis and offers scheduling options for different risk attitudes, enhancing decision-making capabilities.

Authors

Institutions

Publication Details

Journal
Reliability Engineering & System Safety
Published
2025-05-17
DOI
https://doi.org/10.1016/j.ress.2025.111269
Citations
7
Primary Topic
Risk and Safety Analysis
Type
article
Field-Weighted Citation Impact
9.79
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Network analysis-enhanced project risk management for nuclear power plant construction

Enrico Zio, André L.N. Casotti
7 citations
Reliability Engineering & System Safety
Risk and Safety Analysis
9.79
article

Network analysis-enhanced project risk management for nuclear power plant construction

Enrico Zio, André L.N. Casotti
article en
7 citations

Abstract

• A network-based framework to model risks and their interactions in NPP projects • Topological metrics uncover critical risks neglected by classical analysis • Bi-objective project schedule optimization provides alternatives for diverse risk attitudes • A case study for the project of a DC-PWR This paper introduces a comprehensive framework for managing interdependent delay risks in nuclear power plant (NPP) construction by integrating network theory and topological analysis. Spent fuel disposal, nuclear plant safety and nuclear weapons proliferation are known important concerns for nuclear power development, but costs remain the fundamental problem, as NPP projects are plagued by schedule delays that substantially increase total costs. Such complex megaprojects are exposed to numerous risks of different sources that behave interdependently. Most of the studies understand the risks of delay in NPP construction projects in isolation without taking interdependencies into account. The proposed methodology employs a Design Structure Matrix (DSM) to construct a Risk Interaction Network (RIN), enabling a topological assessment to identify critical risks that may cause cascading delays in project tasks. An algorithmic search for these critical risks is conducted, considering the impact of their removal on the RIN's characteristics. We define a bi-objective optimization problem aimed at generating a project schedule that minimizes both the project's makespan and the reachability density of the RIN. The solution is obtained using an evolutionary algorithm. Applied to a Double-Containment Pressurized Water Reactor (DC-PWR) project, this approach effectively uncovers risks neglected by classical analysis and offers scheduling options for different risk attitudes, enhancing decision-making capabilities.

Reliability Engineering & System SafetyVol. 263
Centre de Recherche sur les Risques et les Crises (FR), Politecnico di Milano (IT)
Openalex Percentile: Top 2%
Risk and Safety Analysis
9.79
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.