SCHEDULING ANALYSIS USING THE PRECEDENCE DIAGRAM METHOD (PDM) METHOD IN THE PHASE II BRIDGE CONSTRUCTION PROJECT IN PEJAMBUAN VILLAGE, SUNGAI TABUK DISTRICT, BANJAR REGENCY, SOUTH KALIMANTAN

In its implementation, starting from the planning stage, the implementation of scheduling, to the supervision and implementation of good controls, construction projects need to be well managed in their work. In the process of Building the Phase II Bridge Project in Pejambuan Village, Sungai Tabuk District, there was a slight delay in the eighth week due to equipment damage and delays in the material supply mobilization process. This project only has a time schedule in the form of an S Curve which is not helpful in controlling work in the field.This study aims to analyze scheduling using the Precedence Diagram Method (PDM) method assisted by the Microsoft Project 2021 application and identify critical and non-critical paths of work so that the implementation of the project can be carried out with an effective duration.Based on the results of the analysis of this study, the total duration of work is 138 working days with the total duration of work calculated using calendar days for 174 days, and the total duration of project realization is 180 calendar days. CV planning calculation. Al Fatih Karya is scheduled to be completed by September 30, 2024, while scheduling with the PDM method is completed by September 24, 2024. The critical trajectory in the results of this analysis is found in 13 activities starting from ordinary excavation work and ending with the installation of bridge nameplates. Keywords : Bridge, Microsoft Project 2021, Scheduling, Delay, PDM

Authors

Publication Details

Journal
CERUCUK
Published
2025-04-17
DOI
https://doi.org/10.20527/crc.v9i2.14841
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

SCHEDULING ANALYSIS USING THE PRECEDENCE DIAGRAM METHOD (PDM) METHOD IN THE PHASE II BRIDGE CONSTRUCTION PROJECT IN PEJAMBUAN VILLAGE, SUNGAI TABUK DISTRICT, BANJAR REGENCY, SOUTH KALIMANTAN

Abdul Razak Abdul Karim, Alfisyah Oktarina Pinanggi, Endah Widiastuti
CERUCUK
Management and Optimization Techniques
article

SCHEDULING ANALYSIS USING THE PRECEDENCE DIAGRAM METHOD (PDM) METHOD IN THE PHASE II BRIDGE CONSTRUCTION PROJECT IN PEJAMBUAN VILLAGE, SUNGAI TABUK DISTRICT, BANJAR REGENCY, SOUTH KALIMANTAN

Abdul Razak Abdul Karim, Alfisyah Oktarina Pinanggi, Endah Widiastuti
article en

Abstract

In its implementation, starting from the planning stage, the implementation of scheduling, to the supervision and implementation of good controls, construction projects need to be well managed in their work. In the process of Building the Phase II Bridge Project in Pejambuan Village, Sungai Tabuk District, there was a slight delay in the eighth week due to equipment damage and delays in the material supply mobilization process. This project only has a time schedule in the form of an S Curve which is not helpful in controlling work in the field.This study aims to analyze scheduling using the Precedence Diagram Method (PDM) method assisted by the Microsoft Project 2021 application and identify critical and non-critical paths of work so that the implementation of the project can be carried out with an effective duration.Based on the results of the analysis of this study, the total duration of work is 138 working days with the total duration of work calculated using calendar days for 174 days, and the total duration of project realization is 180 calendar days. CV planning calculation. Al Fatih Karya is scheduled to be completed by September 30, 2024, while scheduling with the PDM method is completed by September 24, 2024. The critical trajectory in the results of this analysis is found in 13 activities starting from ordinary excavation work and ending with the installation of bridge nameplates. Keywords : Bridge, Microsoft Project 2021, Scheduling, Delay, PDM

CERUCUKVol. 9(2)
Openalex Percentile: Top 85%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.