High-Level Risk Analysis in the Construction Project of RSUD Dr. H. Slamet Martodirdjo in Pamekasan

The construction of the Regional General Hospital Dr. H. Slamet Martodirdjo in Pamekasan Regency faces several challenges, particularly concerning high-level risks that may impact project success. This study aims to identify and analyze major risks affecting project completion and propose effective mitigation strategies. Using a survey method, data were collected from key stakeholders and processed using the Severity Index and Probability and Impact Matrix to assess risk levels. The findings identified 25 potential risks, with eight categorized as high-level risks: implementation method errors, difficulties in installing cross foundations, delays in critical path tasks, late material procurement, labor shortages, non-compliance with occupational safety regulations, lack of teamwork among workers, and adverse weather conditions. These risks significantly impact the project timeline, budget, and overall quality. The study also reveals that poor coordination among stakeholders, inefficient risk management practices, and regulatory constraints contribute to project delays. To mitigate these risks, strategic planning, improved procurement management, workforce training, and strict adherence to occupational safety regulations are recommended. Additionally, the adoption of technology-driven solutions, such as digital monitoring systems and e-procurement platforms, can enhance project oversight and efficiency. By implementing a systematic risk management framework, construction projects can minimize potential disruptions, ensure timely project delivery, and maintain cost efficiency. The findings of this study provide valuable insights for project managers, contractors, and policymakers in the construction industry, particularly for large-scale healthcare infrastructure projects. A proactive risk mitigation approach is essential to achieving successful project execution and sustainable infrastructure development.

Authors

Institutions

Publication Details

Journal
Asian Journal of Social and Humanities
Published
2025-05-10
DOI
https://doi.org/10.59888/ajosh.v3i7.544
Primary Topic
Construction Engineering and Safety
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

High-Level Risk Analysis in the Construction Project of RSUD Dr. H. Slamet Martodirdjo in Pamekasan

Jaka Purnama, Budi Witjaksana, Ridwan Ridwan
4 links
Asian Journal of Social and Humanities
Construction Engineering and Safety
article

High-Level Risk Analysis in the Construction Project of RSUD Dr. H. Slamet Martodirdjo in Pamekasan

Jaka Purnama, Budi Witjaksana, Ridwan Ridwan
article en

Abstract

The construction of the Regional General Hospital Dr. H. Slamet Martodirdjo in Pamekasan Regency faces several challenges, particularly concerning high-level risks that may impact project success. This study aims to identify and analyze major risks affecting project completion and propose effective mitigation strategies. Using a survey method, data were collected from key stakeholders and processed using the Severity Index and Probability and Impact Matrix to assess risk levels. The findings identified 25 potential risks, with eight categorized as high-level risks: implementation method errors, difficulties in installing cross foundations, delays in critical path tasks, late material procurement, labor shortages, non-compliance with occupational safety regulations, lack of teamwork among workers, and adverse weather conditions. These risks significantly impact the project timeline, budget, and overall quality. The study also reveals that poor coordination among stakeholders, inefficient risk management practices, and regulatory constraints contribute to project delays. To mitigate these risks, strategic planning, improved procurement management, workforce training, and strict adherence to occupational safety regulations are recommended. Additionally, the adoption of technology-driven solutions, such as digital monitoring systems and e-procurement platforms, can enhance project oversight and efficiency. By implementing a systematic risk management framework, construction projects can minimize potential disruptions, ensure timely project delivery, and maintain cost efficiency. The findings of this study provide valuable insights for project managers, contractors, and policymakers in the construction industry, particularly for large-scale healthcare infrastructure projects. A proactive risk mitigation approach is essential to achieving successful project execution and sustainable infrastructure development.

Asian Journal of Social and HumanitiesVol. 3(7)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 89%
Construction Engineering and Safety
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.