Determination of the optimal PID control law for RPM of hydroelectric power plant units

This article examines the solutions and the typical mistakes in solving the problem that became evident during the blackout of the Georgia’s power system on July 27, 2014. One of the problems turned out to be the inability of hydroelectric power plants (HPP) connected to the grid to operate autonomously and ensure energy consumption for their own needs and for priority consumers. The main problem was that, in order to restore the disconnected part of the power system from a zero state, these HPPs did not have at least one unit capable of quickly starting up after receiving the corresponding instruction from the dispatching licensee. This unit was needed to connect to the grid and provide the reference frequency and voltage for synchronizing the units of the stopped HPPs, all in the absence of voltage in the grid. Undoubtedly, the fulfillment of all these requirements depends on the control systems of the units, in particular, on the quality of the control of the RPM of the units.

Authors

Publication Details

Journal
International journal of engineering and science invention
Published
2025-04-01
DOI
https://doi.org/10.35629/6734-140495100
Primary Topic
Advanced Data Processing Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Determination of the optimal PID control law for RPM of hydroelectric power plant units

Paata Jokhadze, Aleksander Jokhadze
International journal of engineering and science invention
Advanced Data Processing Techniques
article

Determination of the optimal PID control law for RPM of hydroelectric power plant units

Paata Jokhadze, Aleksander Jokhadze
article en

Abstract

This article examines the solutions and the typical mistakes in solving the problem that became evident during the blackout of the Georgia’s power system on July 27, 2014. One of the problems turned out to be the inability of hydroelectric power plants (HPP) connected to the grid to operate autonomously and ensure energy consumption for their own needs and for priority consumers. The main problem was that, in order to restore the disconnected part of the power system from a zero state, these HPPs did not have at least one unit capable of quickly starting up after receiving the corresponding instruction from the dispatching licensee. This unit was needed to connect to the grid and provide the reference frequency and voltage for synchronizing the units of the stopped HPPs, all in the absence of voltage in the grid. Undoubtedly, the fulfillment of all these requirements depends on the control systems of the units, in particular, on the quality of the control of the RPM of the units.

International journal of engineering and science inventionVol. 14(4)
Openalex Percentile: Top 89%
Advanced Data Processing Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.