Correlation Between Progress of Construction Works and Their Financial Spend in the Execution of Residential Buildings

The aim of the research was to determine and proof the real correlation of construction works and their financial spend in relation of the selected group of Residential Buildings X. Deviations and their impact on the correlation in relation to construction and financial throughput were determined and analysed using the basic indicators of the Earned Value Method (EVM), i.e.: estimated final cost of estimated at completion (EAC) projects and correlation with their deadlines for estimated time at completion (ETTC). Additional studies have attempted to approximate the final cost of the EAC more accurately, which is referred to in this study as EAC-S. The obtained results of observations over the entire period of implementation of the selected housing estate were also analysed in statistics used in standard deviation coefficients and Pearson linear correlation r. Such an experiment was performed both for investment X at the moment of flattening of the S curve for cumulative works. Having a dataset from the period of the excessive curve in the case of Residential Buildings X, the result closest to the actual final costs was obtained. The designated indicator overestimated the budget by only 0. 205%. Thus, the EAC Estimated Final Cost Index indicated a value of 0. 422%.

Authors

Publication Details

Journal
Civil And Environmental Engineering Reports
Published
2025-04-27
DOI
https://doi.org/10.59440/ceer/203344
Primary Topic
Scheduling and Optimization Algorithms
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Correlation Between Progress of Construction Works and Their Financial Spend in the Execution of Residential Buildings

Mariusz Szóstak, Jarosław Konior
Civil And Environmental Engineering Reports
Scheduling and Optimization Algorithms
article

Correlation Between Progress of Construction Works and Their Financial Spend in the Execution of Residential Buildings

Mariusz Szóstak, Jarosław Konior
article en

Abstract

The aim of the research was to determine and proof the real correlation of construction works and their financial spend in relation of the selected group of Residential Buildings X. Deviations and their impact on the correlation in relation to construction and financial throughput were determined and analysed using the basic indicators of the Earned Value Method (EVM), i.e.: estimated final cost of estimated at completion (EAC) projects and correlation with their deadlines for estimated time at completion (ETTC). Additional studies have attempted to approximate the final cost of the EAC more accurately, which is referred to in this study as EAC-S. The obtained results of observations over the entire period of implementation of the selected housing estate were also analysed in statistics used in standard deviation coefficients and Pearson linear correlation r. Such an experiment was performed both for investment X at the moment of flattening of the S curve for cumulative works. Having a dataset from the period of the excessive curve in the case of Residential Buildings X, the result closest to the actual final costs was obtained. The designated indicator overestimated the budget by only 0. 205%. Thus, the EAC Estimated Final Cost Index indicated a value of 0. 422%.

Civil And Environmental Engineering ReportsVol. 35(2)
Openalex Percentile: Top 86%
Scheduling and Optimization Algorithms
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.