Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project

In the implementation of construction projects, complex challenges are often faced, one of which is project delays. This research aims to analyze the application of the Fast Track Construction (FTC) method based on time variables in the delay of the SII Office Surabaya building construction project. This research uses a quantitative method by collecting secondary data from the project contractor. The analysis was conducted on the remaining structural and architectural work using the Critical Path Method (CPM) and Microsoft Project. The research results show that of the three acceleration analyses with the FTC 50% method, 4 hours/day overtime and 6 hours/day overtime, the most effective and efficient application is with 4 hours/day overtime. With the addition of overtime, it is known that the more overtime is added, the less it reduces the duration of work items but can reduce the indirect costs of the project. And based on the results of statistical analysis using the Paired T Test, it was found that Ha was accepted and Ho was rejected, which means that the data is significant.

Authors

Institutions

Publication Details

Journal
THE SPIRIT OF SOCIETY JOURNAL
Published
2024-12-26
DOI
https://doi.org/10.29138/scj.v8i1.2941
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project

Julistyana Tistogondo, Rizal Bahaswan, Pasca Fitri Febriani
THE SPIRIT OF SOCIETY JOURNAL
BIM and Construction Integration
article

Implementation Analysis of Fast Track and Variable Work Overtime on Delays in the Building Construction Project

Julistyana Tistogondo, Rizal Bahaswan, Pasca Fitri Febriani
article en

Abstract

In the implementation of construction projects, complex challenges are often faced, one of which is project delays. This research aims to analyze the application of the Fast Track Construction (FTC) method based on time variables in the delay of the SII Office Surabaya building construction project. This research uses a quantitative method by collecting secondary data from the project contractor. The analysis was conducted on the remaining structural and architectural work using the Critical Path Method (CPM) and Microsoft Project. The research results show that of the three acceleration analyses with the FTC 50% method, 4 hours/day overtime and 6 hours/day overtime, the most effective and efficient application is with 4 hours/day overtime. With the addition of overtime, it is known that the more overtime is added, the less it reduces the duration of work items but can reduce the indirect costs of the project. And based on the results of statistical analysis using the Paired T Test, it was found that Ha was accepted and Ho was rejected, which means that the data is significant.

THE SPIRIT OF SOCIETY JOURNALVol. 8(1)
Universitas Narotama (ID)
Openalex Percentile: Top 69%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.