Performance Analysis of Costs and Implementation Time Using Earned Value Method on the Distribution Pipe Network Expansion in Samarinda City

The problems raised in this research relate to the implementation performance of the Samarinda City distribution piping network expansion project. With the increasing need for clean water and the increasing population, PDAM Kota Samarinda must be able to meet demand with quality, quantity, continuity and accessible prices, as well as adequate water pressure. In an effort to provide clean water services, the government must pay special attention to developing the distribution network. The previous distribution piping network in Samarinda City is considered to need to be expanded to meet the need for clean water, especially during the dry season where there is a shortage of clean water in the Samarinda area. Based on the background of this problem, the title of this research is Analysis of cost performance and implementation time using the EVM Method (Earned Value Method) in the Samarinda City Distribution Pipeline Network Expansion Work. This research was carried out with the aim of determining the cost and time for completing the project. The research method uses calculation and analysis of ACWP, BCWP, BCWS, Cost Performance Index, Cost Variance, Earned Value, Earned Value Method, EVM, Schedule Variance, Variance at Completion. Based on the analysis of the data obtained, it can be concluded that the cost performance is not in accordance with the budget and the estimated cost until the project is completed is IDR. 20,583,636,709, greater than the planned Rp. 16,566,678,000. Time performance in weeks 4 to 20 experienced delays. Estimated project completion time is 163 days or 24 weeks. longer than planned, namely 161 days.

Authors

Institutions

Publication Details

Journal
THE SPIRIT OF SOCIETY JOURNAL
Published
2024-12-26
DOI
https://doi.org/10.29138/scj.v8i1.3176
Primary Topic
Elevator Systems and Control
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Performance Analysis of Costs and Implementation Time Using Earned Value Method on the Distribution Pipe Network Expansion in Samarinda City

Risma Marleno, Wateno Oetomo, Dedy Sugi Hartawan
THE SPIRIT OF SOCIETY JOURNAL
Elevator Systems and Control
article

Performance Analysis of Costs and Implementation Time Using Earned Value Method on the Distribution Pipe Network Expansion in Samarinda City

Risma Marleno, Wateno Oetomo, Dedy Sugi Hartawan
article en

Abstract

The problems raised in this research relate to the implementation performance of the Samarinda City distribution piping network expansion project. With the increasing need for clean water and the increasing population, PDAM Kota Samarinda must be able to meet demand with quality, quantity, continuity and accessible prices, as well as adequate water pressure. In an effort to provide clean water services, the government must pay special attention to developing the distribution network. The previous distribution piping network in Samarinda City is considered to need to be expanded to meet the need for clean water, especially during the dry season where there is a shortage of clean water in the Samarinda area. Based on the background of this problem, the title of this research is Analysis of cost performance and implementation time using the EVM Method (Earned Value Method) in the Samarinda City Distribution Pipeline Network Expansion Work. This research was carried out with the aim of determining the cost and time for completing the project. The research method uses calculation and analysis of ACWP, BCWP, BCWS, Cost Performance Index, Cost Variance, Earned Value, Earned Value Method, EVM, Schedule Variance, Variance at Completion. Based on the analysis of the data obtained, it can be concluded that the cost performance is not in accordance with the budget and the estimated cost until the project is completed is IDR. 20,583,636,709, greater than the planned Rp. 16,566,678,000. Time performance in weeks 4 to 20 experienced delays. Estimated project completion time is 163 days or 24 weeks. longer than planned, namely 161 days.

THE SPIRIT OF SOCIETY JOURNALVol. 8(1)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 63%
Elevator Systems and Control
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Performance Analysis of Costs and Implementation Time Using Earned Value Method on the Distribution Pipe Network Expansion in Samarinda City — Risma Marleno, Wateno Oetomo, et al. · THE SPIRIT OF SOCIETY JOURNAL (2024) | TGRS Research Map | TGRS