Factors Affecting Time and Cost Overrun – Indian Scenario.

Abstract - In the Indian construction industry, time and cost overruns are an ongoing issue, especially for major road infrastructure projects. Using information from primary data gathered through structured surveys as well as literature, this study examines the main causes of these overruns. Finding the most significant causes, evaluating their relative effects, and making useful suggestions for minimizing them were the goals of the study. To determine the fundamental factors causing delays in projects and cost increases, a thorough literature review was carried out. A questionnaire survey was created and distributed to industry professionals working on road infrastructure projects in light of these findings. In order to rank the degree to which each aspect affected time and cost performance, the responses that were gathered were examined. The findings revealed that the main causes of project overruns were changes to the scope during execution, construction mistakes, problems with bill settlement, construction accidents, and rising fuel and material costs. In order to reduce overruns, the study's conclusion highlights the necessity of better planning, effective stakeholder communication and contractual risk allocation. Policymakers, contractors and project managers looking to improve the effectiveness and sustainability of infrastructure development in India will find the findings to be a useful resource. Key Words: Time overrun, Cost overrun, Indian construction Industry, Likert's scale.

Authors

Publication Details

Journal
INTERANTIONAL JOURNAL OF SCIENTIFIC RESEARCH IN ENGINEERING AND MANAGEMENT
Published
2025-05-09
DOI
https://doi.org/10.55041/ijsrem47227
Primary Topic
Quality and Supply Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Factors Affecting Time and Cost Overrun – Indian Scenario.

Mr. Sanved Sharad More
INTERANTIONAL JOURNAL OF SCIENTIFIC RESEARCH IN ENGINEERING AND MANAGEMENT
Quality and Supply Management
article

Factors Affecting Time and Cost Overrun – Indian Scenario.

Mr. Sanved Sharad More
article en

Abstract

Abstract - In the Indian construction industry, time and cost overruns are an ongoing issue, especially for major road infrastructure projects. Using information from primary data gathered through structured surveys as well as literature, this study examines the main causes of these overruns. Finding the most significant causes, evaluating their relative effects, and making useful suggestions for minimizing them were the goals of the study. To determine the fundamental factors causing delays in projects and cost increases, a thorough literature review was carried out. A questionnaire survey was created and distributed to industry professionals working on road infrastructure projects in light of these findings. In order to rank the degree to which each aspect affected time and cost performance, the responses that were gathered were examined. The findings revealed that the main causes of project overruns were changes to the scope during execution, construction mistakes, problems with bill settlement, construction accidents, and rising fuel and material costs. In order to reduce overruns, the study's conclusion highlights the necessity of better planning, effective stakeholder communication and contractual risk allocation. Policymakers, contractors and project managers looking to improve the effectiveness and sustainability of infrastructure development in India will find the findings to be a useful resource. Key Words: Time overrun, Cost overrun, Indian construction Industry, Likert's scale.

INTERANTIONAL JOURNAL OF SCIENTIFIC RESEARCH IN ENGINEERING AND MANAGEMENTVol. 09(05)
Openalex Percentile: Top 84%
Quality and Supply Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Factors Affecting Time and Cost Overrun – Indian Scenario. — Mr. Sanved Sharad More · INTERANTIONAL JOURNAL OF SCIENTIFIC RESEARCH IN ENGINEERING AND MANAGEMENT (2025) | TGRS Research Map | TGRS