Impacts of Construction Timelines on Generation Availability

The rapid growth of digital infrastructure, driven by increasing demands for artificial intelligence (AI) and machine learning (ML) capabilities, has fueled an unprecedented need for data centers. Data centers are expected to consume up to 12 percent of total US electricity by 2028 with their expected electricity usage climbing between 325 and 580 terawatt hours (TWh) in the next four years, representing a growth rate between 13 percent and 27 percent. These facilities form the backbone of modern computing and cloud services, consuming large amounts of energy, often necessitating the construction of power plants and electric grid infrastructure to meet their needs. As data centers scale to capacities of 100 megawatts (MW) or more, their construction timelines and complexities increasingly resemble those of power plants designed to supply similar energy levels.

Authors

Publication Details

Journal
Climate and Energy
Published
2025-05-07
DOI
https://doi.org/10.1002/gas.22463
Citations
1
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
1.01
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Impacts of Construction Timelines on Generation Availability

Michael Lavillotti
1 citations
Climate and Energy
BIM and Construction Integration
1.01
article

Impacts of Construction Timelines on Generation Availability

Michael Lavillotti
article en
1 citations

Abstract

The rapid growth of digital infrastructure, driven by increasing demands for artificial intelligence (AI) and machine learning (ML) capabilities, has fueled an unprecedented need for data centers. Data centers are expected to consume up to 12 percent of total US electricity by 2028 with their expected electricity usage climbing between 325 and 580 terawatt hours (TWh) in the next four years, representing a growth rate between 13 percent and 27 percent. These facilities form the backbone of modern computing and cloud services, consuming large amounts of energy, often necessitating the construction of power plants and electric grid infrastructure to meet their needs. As data centers scale to capacities of 100 megawatts (MW) or more, their construction timelines and complexities increasingly resemble those of power plants designed to supply similar energy levels.

Climate and EnergyVol. 41(11)
Openalex Percentile: Top 25%
BIM and Construction Integration
1.01
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.