Deconstructing construction wastes: Exploring waste generation causes and their impact on project performances

The construction industry has long been struggling with excessive costs, delays, and compromised quality due to wasteful practices, particularly in developing nations. While international efforts have focused on identifying waste-related factors, there's a research gap in pinpointing micro-level causes and analyzing their specific impacts on cost, quality, and time. This study delves into the prevalent and crucial causes of construction waste in Pakistan, evaluating their collective influence on project cost, schedule, quality, and material management. A mix of literature study findings, on-site inspections, and a survey from industry experts was used to determine the causes of non-value-adding/waste generation in construction. Using two rounds of questionnaire survey, 65 valid responses (48% of response rate) were obtained. Following the initial round, the most significant causes and their consequences on waste-related features were identified using the Relative Importance Index (RII) and mean value indexing. To confirm the influence of these waste-generating causes on Pakistani construction projects, assessments from 21 industrial experts were conducted in the second round. The data alignment between the two phases confirmed the impact of the indicated causes on waste. The study determined that inadequate worker training and awareness, planning long duration leading to material escalation, and poor workmanship are the main causes of construction waste in Pakistan. Insights from 21 construction industry experts were also acquired, offering helpful strategies to cut waste in these projects. The outcome of this study clarifies the main reasons for the negative effects of construction waste on the sector and offers recommendations for future steps to reduce their frequency.

Authors

Institutions

Publication Details

Journal
PLoS ONE
Published
2025-05-07
DOI
https://doi.org/10.1371/journal.pone.0322295
Citations
2
Primary Topic
Recycled Aggregate Concrete Performance
Type
article
Field-Weighted Citation Impact
2.01
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Deconstructing construction wastes: Exploring waste generation causes and their impact on project performances

Hafız Zahoor, Mughees Aslam, Muhammad Sohail Anwar Malik, Farrokh Jaleel et al.
2 citations
PLoS ONE
Recycled Aggregate Concrete Performance
2.01
article

Deconstructing construction wastes: Exploring waste generation causes and their impact on project performances

Hafız Zahoor, Mughees Aslam, Muhammad Sohail Anwar Malik, Farrokh Jaleel, Usman Aftab, Aman Ulhaq
article en
2 citations

Abstract

The construction industry has long been struggling with excessive costs, delays, and compromised quality due to wasteful practices, particularly in developing nations. While international efforts have focused on identifying waste-related factors, there's a research gap in pinpointing micro-level causes and analyzing their specific impacts on cost, quality, and time. This study delves into the prevalent and crucial causes of construction waste in Pakistan, evaluating their collective influence on project cost, schedule, quality, and material management. A mix of literature study findings, on-site inspections, and a survey from industry experts was used to determine the causes of non-value-adding/waste generation in construction. Using two rounds of questionnaire survey, 65 valid responses (48% of response rate) were obtained. Following the initial round, the most significant causes and their consequences on waste-related features were identified using the Relative Importance Index (RII) and mean value indexing. To confirm the influence of these waste-generating causes on Pakistani construction projects, assessments from 21 industrial experts were conducted in the second round. The data alignment between the two phases confirmed the impact of the indicated causes on waste. The study determined that inadequate worker training and awareness, planning long duration leading to material escalation, and poor workmanship are the main causes of construction waste in Pakistan. Insights from 21 construction industry experts were also acquired, offering helpful strategies to cut waste in these projects. The outcome of this study clarifies the main reasons for the negative effects of construction waste on the sector and offers recommendations for future steps to reduce their frequency.

PLoS ONEVol. 20(5)
International Islamic University, Islamabad (PK), National University of Sciences and Technology (PK)
Industry, innovation and infrastructure
Openalex Percentile: Top 15%
Recycled Aggregate Concrete Performance
2.01
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.