Penerapan Metode LSM (Linier Scheduling Method) Pada Pembangunan Proyek Konstruksi (Studi Kasus: Perumahan Citra Agrindo III)

Efficient scheduling methods are crucial in housing construction projects to minimize delays and optimize time management. This study investigates the impact of scheduling methods on project duration, highlighting the inefficiencies caused by mismatches between scheduling techniques and project characteristics. The research focuses on implementing the Linear Scheduling Method (LSM) for housing project scheduling and comparing it with conventional scheduling methods. LSM is particularly effective for repetitive construction projects, as it enables continuous work progression and minimizes task interference. By systematically organizing workgroups and sequencing activities, LSM ensures smoother workflow transitions and reduces idle time. A case study on the Citra Agrindo III Housing Project reveals that using LSM significantly improves time efficiency. The completion time is reduced from 384 days to 207 days, demonstrating a remarkable 177-day reduction compared to the existing scheduling approach. The findings highlight LSM's advantages in managing project timelines more effectively by streamlining workflow, preventing overlapping activities, and optimizing resource allocation. This research underscores the importance of selecting appropriate scheduling methods based on project characteristics to achieve better efficiency. The application of LSM in housing project scheduling proves to be a more effective approach, offering substantial time savings and improved project execution. Future research can further explore LSM’s adaptability across different construction project scales and complexities to enhance its implementation in the industry.

Authors

Institutions

Publication Details

Journal
Research Review Jurnal Ilmiah Multidisiplin
Published
2025-03-25
DOI
https://doi.org/10.54923/researchreview.v4i1.132
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Penerapan Metode LSM (Linier Scheduling Method) Pada Pembangunan Proyek Konstruksi (Studi Kasus: Perumahan Citra Agrindo III)

Moh. Yusuf Tuloli, Arfan Usman Sumaga, Vetry M. Gobel
Research Review Jurnal Ilmiah Multidisiplin
Occupational Health and Safety Management
article

Penerapan Metode LSM (Linier Scheduling Method) Pada Pembangunan Proyek Konstruksi (Studi Kasus: Perumahan Citra Agrindo III)

Moh. Yusuf Tuloli, Arfan Usman Sumaga, Vetry M. Gobel
article en

Abstract

Efficient scheduling methods are crucial in housing construction projects to minimize delays and optimize time management. This study investigates the impact of scheduling methods on project duration, highlighting the inefficiencies caused by mismatches between scheduling techniques and project characteristics. The research focuses on implementing the Linear Scheduling Method (LSM) for housing project scheduling and comparing it with conventional scheduling methods. LSM is particularly effective for repetitive construction projects, as it enables continuous work progression and minimizes task interference. By systematically organizing workgroups and sequencing activities, LSM ensures smoother workflow transitions and reduces idle time. A case study on the Citra Agrindo III Housing Project reveals that using LSM significantly improves time efficiency. The completion time is reduced from 384 days to 207 days, demonstrating a remarkable 177-day reduction compared to the existing scheduling approach. The findings highlight LSM's advantages in managing project timelines more effectively by streamlining workflow, preventing overlapping activities, and optimizing resource allocation. This research underscores the importance of selecting appropriate scheduling methods based on project characteristics to achieve better efficiency. The application of LSM in housing project scheduling proves to be a more effective approach, offering substantial time savings and improved project execution. Future research can further explore LSM’s adaptability across different construction project scales and complexities to enhance its implementation in the industry.

Research Review Jurnal Ilmiah MultidisiplinVol. 4(1)
State University of Gorontalo (ID)
Openalex Percentile: Top 86%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.