A comparative analysis of MIP formulations for the multi-mode resource-constrained independent task scheduling problem
Abstract We consider the problem of scheduling independent multi-mode tasks with multiple renewable resource constraints, aiming to minimize the weighted sum of tardinesses. This problem commonly arises in the context of multiproject scheduling. We propose three pseudo-polynomial mixed-integer programming formulations and conduct a theoretical comparative analysis of their respective linear programming relaxations. We present the results of extensive computational experiments that provide evidence that a formulation based on Dantzig–Wolfe reformulation exhibits very good empirical performance consistently solving all instances with fewer than 30 tasks. In addition, it achieved an average success rate of 94.28% for instances with tasks ranging from 40 to 100, compared to other formulations that on average achieved success rates of 64.28% and 58.57%.
Authors
- Maryam Al-Khatib (ORCID: https://orcid.org/0000-0002-1436-0766)
- Mohamed Kharbeche (ORCID: https://orcid.org/0000-0003-1469-7163)
- Mohamed Haouari (ORCID: https://orcid.org/0000-0003-0767-8220)
Institutions
- Qatar University (QA)
Publication Details
- Journal
- Operational Research
- Published
- 2025-05-05
- DOI
- https://doi.org/10.1007/s12351-025-00924-2
- Primary Topic
- Resource-Constrained Project Scheduling