Analysis of Delays in Construction Time of the Banjarsari Water Gate Project, Sidoarjo District Using Critical Path Method

The Banjarsari sluice gate, located on the Sidoarjo district's shipping river, faces various challenges that can affect its performance. These challenges include sedimentation, damage to building structures, and decreased water quality due to domestic and industrial waste. The implementation of the Banjarsari Water Gate maintenance project, especially the floor work, experienced seepage at the bottom of the water gate floor, resulting in structural failure of the water gate building. CPM method duration planning is a recommendation in choosing from the many methods available, because there is a calculation of the earliest time the project starts, the latest time the project begins, the earliest time completed, and the latest time completed, so that the time lag of all activities can be known. Analyze the acceleration of work duration by adding workers to the work on the critical path. The purpose of this research is to analyze the length of time required by the CPM (Critical Path Method) method for the work of the Banjarsari floodgate. In this study, the time analysis uses the CPM (Critical Path Method) method and is assisted by Microsoft Project 2021 Software. The analysis results obtained work through the critical path, namely demolition work and cyclope concrete casting, and obtained the results of the duration of work on the Banjarsari floodgate work after crashing to 66 working days from the initial duration of 72 working days.

Authors

Institutions

Publication Details

Journal
Enrichment Journal of Multidisciplinary Research and Development
Published
2025-04-15
DOI
https://doi.org/10.55324/enrichment.v3i1.334
Primary Topic
Mining Techniques and Economics
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Delays in Construction Time of the Banjarsari Water Gate Project, Sidoarjo District Using Critical Path Method

Esti Wulandari, Laksono Djoko Nugroho, Dwi Erry Nopriyanto
Enrichment Journal of Multidisciplinary Research and Development
Mining Techniques and Economics
article

Analysis of Delays in Construction Time of the Banjarsari Water Gate Project, Sidoarjo District Using Critical Path Method

Esti Wulandari, Laksono Djoko Nugroho, Dwi Erry Nopriyanto
article en

Abstract

The Banjarsari sluice gate, located on the Sidoarjo district's shipping river, faces various challenges that can affect its performance. These challenges include sedimentation, damage to building structures, and decreased water quality due to domestic and industrial waste. The implementation of the Banjarsari Water Gate maintenance project, especially the floor work, experienced seepage at the bottom of the water gate floor, resulting in structural failure of the water gate building. CPM method duration planning is a recommendation in choosing from the many methods available, because there is a calculation of the earliest time the project starts, the latest time the project begins, the earliest time completed, and the latest time completed, so that the time lag of all activities can be known. Analyze the acceleration of work duration by adding workers to the work on the critical path. The purpose of this research is to analyze the length of time required by the CPM (Critical Path Method) method for the work of the Banjarsari floodgate. In this study, the time analysis uses the CPM (Critical Path Method) method and is assisted by Microsoft Project 2021 Software. The analysis results obtained work through the critical path, namely demolition work and cyclope concrete casting, and obtained the results of the duration of work on the Banjarsari floodgate work after crashing to 66 working days from the initial duration of 72 working days.

Enrichment Journal of Multidisciplinary Research and DevelopmentVol. 3(1)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 90%
Mining Techniques and Economics
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.