Time and Cost Control Analysis of Disaster Emergency Response Handling Project Construction in Mojokerto District Using Critical Path Method

Landslides along the Sumber Pasinan River in Mojokerto Regency, East Java, pose significant risks due to soil erosion and increased flooding during the rainy season. This study aims to analyze the acceleration of construction for a disaster emergency response project using the Critical Path Method (CPM) to minimize time and costs. Employing a quantitative research approach, primary data was gathered through direct observations at the project site, complemented by secondary data from relevant literature and project documents. The findings indicate that the implementation period was successfully reduced from 71 working days to 47 days, achieving a time acceleration of 24 days. This required the addition of 11 workers for the critical task of installing river stone masonry, which constituted 70.16% of the project's workload. The application of CPM proved effective in managing time and resources efficiently. The implications of this research highlight the importance of employing structured project management methodologies in disaster response construction projects. By demonstrating the effectiveness of CPM in accelerating project timelines while controlling costs, this study provides a valuable reference for future projects facing similar challenges. It also opens avenues for further research into the long-term impacts of workforce augmentation on project quality and cost-effectiveness in disaster management contexts.

Authors

Institutions

Publication Details

Journal
Enrichment Journal of Multidisciplinary Research and Development
Published
2025-04-15
DOI
https://doi.org/10.55324/enrichment.v3i1.331
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Time and Cost Control Analysis of Disaster Emergency Response Handling Project Construction in Mojokerto District Using Critical Path Method

Esti Wulandari, Laksono Djoko Nugroho, Ean Fadhillah Nurrahmat
Enrichment Journal of Multidisciplinary Research and Development
Management and Optimization Techniques
article

Time and Cost Control Analysis of Disaster Emergency Response Handling Project Construction in Mojokerto District Using Critical Path Method

Esti Wulandari, Laksono Djoko Nugroho, Ean Fadhillah Nurrahmat
article en

Abstract

Landslides along the Sumber Pasinan River in Mojokerto Regency, East Java, pose significant risks due to soil erosion and increased flooding during the rainy season. This study aims to analyze the acceleration of construction for a disaster emergency response project using the Critical Path Method (CPM) to minimize time and costs. Employing a quantitative research approach, primary data was gathered through direct observations at the project site, complemented by secondary data from relevant literature and project documents. The findings indicate that the implementation period was successfully reduced from 71 working days to 47 days, achieving a time acceleration of 24 days. This required the addition of 11 workers for the critical task of installing river stone masonry, which constituted 70.16% of the project's workload. The application of CPM proved effective in managing time and resources efficiently. The implications of this research highlight the importance of employing structured project management methodologies in disaster response construction projects. By demonstrating the effectiveness of CPM in accelerating project timelines while controlling costs, this study provides a valuable reference for future projects facing similar challenges. It also opens avenues for further research into the long-term impacts of workforce augmentation on project quality and cost-effectiveness in disaster management contexts.

Enrichment Journal of Multidisciplinary Research and DevelopmentVol. 3(1)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 87%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.