Analysis of Delays in the Construction Project of the Pumping House in the Sumenep District Using the Critical Path Method

Delays in construction projects pose significant challenges, particularly in remote areas like the Sumenep District. This research analyzed the pump house construction project delays using the Critical Path Method (CPM) to identify the primary factors causing delays, including material supply issues and labor shortages. A qualitative descriptive approach was employed, involving in-depth interviews with project stakeholders and analysis of project documents, including weekly reports and schedules. The findings indicated that the project experienced an average delay of two weeks, primarily due to delays in material supply from Surabaya and concurrent labor shortages caused by multiple simultaneous projects. To address these challenges, the study proposed solutions such as strengthening logistics coordination with local suppliers, increasing the workforce on critical tasks, and utilizing additional heavy equipment. The implications of this research highlight the importance of effective time and resource management in construction projects, particularly in remote locations. Applying the CPM method, this study identifies the root causes of delays and provides practical strategies to enhance project efficiency and reduce costs. This research contributes to the existing literature on construction management in Indonesia, emphasizing the need for adaptive approaches tailored to local conditions.

Authors

Institutions

Publication Details

Journal
Enrichment Journal of Multidisciplinary Research and Development
Published
2025-04-15
DOI
https://doi.org/10.55324/enrichment.v3i1.335
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Delays in the Construction Project of the Pumping House in the Sumenep District Using the Critical Path Method

Jenodius Aldino John, Esti Wulandari, Laksono Djoko Nugroho
Enrichment Journal of Multidisciplinary Research and Development
Management and Optimization Techniques
article

Analysis of Delays in the Construction Project of the Pumping House in the Sumenep District Using the Critical Path Method

Jenodius Aldino John, Esti Wulandari, Laksono Djoko Nugroho
article en

Abstract

Delays in construction projects pose significant challenges, particularly in remote areas like the Sumenep District. This research analyzed the pump house construction project delays using the Critical Path Method (CPM) to identify the primary factors causing delays, including material supply issues and labor shortages. A qualitative descriptive approach was employed, involving in-depth interviews with project stakeholders and analysis of project documents, including weekly reports and schedules. The findings indicated that the project experienced an average delay of two weeks, primarily due to delays in material supply from Surabaya and concurrent labor shortages caused by multiple simultaneous projects. To address these challenges, the study proposed solutions such as strengthening logistics coordination with local suppliers, increasing the workforce on critical tasks, and utilizing additional heavy equipment. The implications of this research highlight the importance of effective time and resource management in construction projects, particularly in remote locations. Applying the CPM method, this study identifies the root causes of delays and provides practical strategies to enhance project efficiency and reduce costs. This research contributes to the existing literature on construction management in Indonesia, emphasizing the need for adaptive approaches tailored to local conditions.

Enrichment Journal of Multidisciplinary Research and DevelopmentVol. 3(1)
Universitas 17 Agustus 1945 Surabaya (ID)
Openalex Percentile: Top 87%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.