House of Risk Approach in Determining Delay Risk Factors

Delays in project completion can lead to significant financial losses, reduced contractor performance, and decreased operational efficiency. This study analyzes the delay factors in the Proton Beam Building construction project at RSPAD Gatot Soebroto, identifying the primary causes and proposing targeted mitigation strategies. A mixed-method approach, combining qualitative interviews and quantitative surveys with key project stakeholders including planning consultants, construction management teams, contractors, and other involved parties is employed. The analysis utilizes the House of Risk (HOR) method to identify and prioritize delay agents and the House of Delay (HOD) method, supplemented by Forum Group Discussions for comprehensive insights. Keyresearch variables encompass human resources, materials, equipment, contract administration, project planning, field conditions, and stakeholder involvement. The study reveals that the primary causes of delays are inadequate planning, design changes, and a shortage of qualified human resources in construction management and planning consulting. The HOR methodology identifies the top three delay agents: Planning not in accordance with regulations (A8), Design changes (A6), and Lack of human resources (A4). To address these issues, the study proposes mitigation strategies, including the creation of a comprehensive checklist for regulatory compliance during planning, ensuring design alignment with applicable regulations, and developing contingency plans to addresspotential human resource shortages. These strategies aim to reduce the most significant delay risks, improve project efficiency, and enhance overall project compliance.

Authors

Institutions

Publication Details

Journal
IAIC Transactions on Sustainable Digital Innovation (ITSDI)
Published
2025-03-20
DOI
https://doi.org/10.34306/itsdi.v6i2.690
Citations
4
Primary Topic
Risk and Safety Analysis
Type
article
Field-Weighted Citation Impact
5.59
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

House of Risk Approach in Determining Delay Risk Factors

Bambang Endro Yuwono, Endah Kurniyaningrum, Rani Kardiani, Tulus Widiarso
4 citations
IAIC Transactions on Sustainable Digital Innovation (ITSDI)
Risk and Safety Analysis
5.59
article

House of Risk Approach in Determining Delay Risk Factors

Bambang Endro Yuwono, Endah Kurniyaningrum, Rani Kardiani, Tulus Widiarso
article en
4 citations

Abstract

Delays in project completion can lead to significant financial losses, reduced contractor performance, and decreased operational efficiency. This study analyzes the delay factors in the Proton Beam Building construction project at RSPAD Gatot Soebroto, identifying the primary causes and proposing targeted mitigation strategies. A mixed-method approach, combining qualitative interviews and quantitative surveys with key project stakeholders including planning consultants, construction management teams, contractors, and other involved parties is employed. The analysis utilizes the House of Risk (HOR) method to identify and prioritize delay agents and the House of Delay (HOD) method, supplemented by Forum Group Discussions for comprehensive insights. Keyresearch variables encompass human resources, materials, equipment, contract administration, project planning, field conditions, and stakeholder involvement. The study reveals that the primary causes of delays are inadequate planning, design changes, and a shortage of qualified human resources in construction management and planning consulting. The HOR methodology identifies the top three delay agents: Planning not in accordance with regulations (A8), Design changes (A6), and Lack of human resources (A4). To address these issues, the study proposes mitigation strategies, including the creation of a comprehensive checklist for regulatory compliance during planning, ensuring design alignment with applicable regulations, and developing contingency plans to addresspotential human resource shortages. These strategies aim to reduce the most significant delay risks, improve project efficiency, and enhance overall project compliance.

IAIC Transactions on Sustainable Digital Innovation (ITSDI)Vol. 6(2)
Universitas Trisakti (ID)
Openalex Percentile: Top 4%
Risk and Safety Analysis
5.59
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.