ANALISIS PERBANDINGAN BEKISTING KONVENSIONAL DENGAN BEKISTING SISTEM PERI PADA GEDUNG BERTINGKAT

Formwork is a tool to help mold concrete with the desired size, shape, or position. In the implementation of formwork work, the selection of the type of formwork will affect the cost, implementation time, and construction quality. There are 3 (three) types of formwork in Indonesia, including conventional formwork, semi-system formwork, and system formwork. In this study, the installation and dismantling methods of conventional formwork and PERI System formwork will be analyzed, a comparison of the calculation of time and costs required for the installation and dismantling of conventional formwork with PERI system formwork in 3 different buildings, and an analysis of the economic feasibility study of PERI system formwork investment.This research is a quantitative research with the aim of knowing the comparative analysis of conventional formwork methods and PERI system formwork, then analyzing the material requirements and costs between conventional formwork and PERI system formwork and conducting an investment feasibility study analysis of the PERI System formwork. The work reviewed is on plate and beam work.The results of the study showed that the cost of procuring PERI System formwork was Rp 6,181,415,050 more expensive than conventional formwork. In the implementation of the installation and dismantling of PERI system formwork, it was faster than conventional formwork, the difference in installation production capacity was 6 m2/day, while the difference in dismantling time was 2m²/day. The investment feasibility study for the procurement of PERI System formwork is still feasible because the Net Present Value (NPV) value obtained was Rp 63,801,026, the Benefit Cost Ratio (BCR) value obtained was 1.007 and the Internal Rate Of Return (IRR) value was 9.48%.Keywords : Formwork, Conventional, PERI System, Investment Feasibility.

Authors

Publication Details

Journal
Pondasi
Published
2024-12-25
DOI
https://doi.org/10.30659/pondasi.v29i2.39824
Primary Topic
Geotechnical and construction materials studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS PERBANDINGAN BEKISTING KONVENSIONAL DENGAN BEKISTING SISTEM PERI PADA GEDUNG BERTINGKAT

Muhammad Miftakhul Ulum, Henny Pratiwi Adi, Moh Faiqun Ni'am
Pondasi
Geotechnical and construction materials studies
article

ANALISIS PERBANDINGAN BEKISTING KONVENSIONAL DENGAN BEKISTING SISTEM PERI PADA GEDUNG BERTINGKAT

Muhammad Miftakhul Ulum, Henny Pratiwi Adi, Moh Faiqun Ni'am
article en

Abstract

Formwork is a tool to help mold concrete with the desired size, shape, or position. In the implementation of formwork work, the selection of the type of formwork will affect the cost, implementation time, and construction quality. There are 3 (three) types of formwork in Indonesia, including conventional formwork, semi-system formwork, and system formwork. In this study, the installation and dismantling methods of conventional formwork and PERI System formwork will be analyzed, a comparison of the calculation of time and costs required for the installation and dismantling of conventional formwork with PERI system formwork in 3 different buildings, and an analysis of the economic feasibility study of PERI system formwork investment.This research is a quantitative research with the aim of knowing the comparative analysis of conventional formwork methods and PERI system formwork, then analyzing the material requirements and costs between conventional formwork and PERI system formwork and conducting an investment feasibility study analysis of the PERI System formwork. The work reviewed is on plate and beam work.The results of the study showed that the cost of procuring PERI System formwork was Rp 6,181,415,050 more expensive than conventional formwork. In the implementation of the installation and dismantling of PERI system formwork, it was faster than conventional formwork, the difference in installation production capacity was 6 m2/day, while the difference in dismantling time was 2m²/day. The investment feasibility study for the procurement of PERI System formwork is still feasible because the Net Present Value (NPV) value obtained was Rp 63,801,026, the Benefit Cost Ratio (BCR) value obtained was 1.007 and the Internal Rate Of Return (IRR) value was 9.48%.Keywords : Formwork, Conventional, PERI System, Investment Feasibility.

PondasiVol. 29(2)
Openalex Percentile: Top 67%
Geotechnical and construction materials studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

ANALISIS PERBANDINGAN BEKISTING KONVENSIONAL DENGAN BEKISTING SISTEM PERI PADA GEDUNG BERTINGKAT — Muhammad Miftakhul Ulum, Henny Pratiwi Adi, et al. · Pondasi (2024) | TGRS Research Map | TGRS